Skip to main content
File #: 24-1019    Version: 1 Name:
Type: Action Item Status: No Action Taken
File created: 7/5/2024 In control: Community Affairs Committee
On agenda: 10/15/2024 Final action: 10/15/2024
Title: Recommendation of selected alternative for Schoonmaker Creek watershed flood mitigation project (CIP Project #3005)
Sponsors: Engineering, Michael Steiner
Attachments: 1. Schoonmaker Creek Next Steps, 2. 10310004 Schoonmaker Creek Watershed Report 20241010_00_Complete, 3. 10310004_SchoonmakerCreek_CommunityAffairsMeeting_DRAFT_20241009, 4. Public Comment Letter - Schoonmaker Creek - WHA.pdf, 5. Public Comment Letter - Schoonmaker Creek - Kolden.pdf
Related files: 24-1459

title
Recommendation of selected alternative for Schoonmaker Creek watershed flood mitigation project (CIP Project #3005)

 

body

Submitted by:

Mike Steiner                     

Department:

Engineering

 

A.                     Issue

Selection of final storm water alternate for Schoonmaker Creek Watershed between Lloyd St and the Menomonee River.

 

B.                     Background and Discussion

In 2022, the Common Council narrowed the list of possible alternatives contained in the report prepared by the Southeastern Wisconsin Reginal Planning Commission (SEWRPC) to mitigate flooding in the Schoonmaker Creek Watershed from 17 alternatives down to two. Common Council directed staff to further analyze these remaining two options to arrive at a recommended solution. The city engaged the consulting engineering firm of MSA to undertake a detailed analysis of these two options.

 

MSA prepared a comprehensive computer model which simulates storm water flows for each option. They then prepared detailed engineering and construction cost estimates for each option. Representatives from MSA will present their findings.

 

The two options are:

Option One: SEWRPC alternative number 15 - tunnel option

Option Two: SEWRPC alternative number 16 - conventional storm sewer option

 

Attached is a flowchart of the next steps to be undertaken for this project once we select an option.

 

C. Strategic Plan (Area of Focus)

Priority 3: Infrastructure, Goal 4. Identify improvement options for the Schoonmaker Watershed.

 

D. Fiscal Impact

Preliminary estimates of probable construction costs from Lloyd St to the Menomonee River for each option are below.

 

Tunnel option - $63.6 million dollars

Conventional storm sewer option - $38.9 million dollars

 

The costs above are for the portions of the project between Lloyd St and the Menomonee River. Additional work between Lloyd St and Center St will be required for either option. This cost is estimated to be $115 million to $135 million in addition to the cost estimates for other options above.

 

E. Recommendations

Staff recommends selection of the conventional storm sewer option as it is the least costly option.