23-90 - 2023 Fiber
• Only a few hand holes remain uninstalled.
• Still awaiting permitting through the railroad. Remaining work pending at this time as coordination continues.
• Boring work started in a few locations. This work looks to resume the week of August 5th.
23-30 - Wauwatosa Bike Share
• Work to resume in fall in coordination with MRMC and the site work that is on-going.
Elm Grove Water Main Extension
• Water main work in Elm Grove continues through Summer/Fall 2024.
24-01 - Potter Road & 109th St.
• Water main work on Potter Road is near complete and ready for pressure testing and safe samples. The jacking and boring of the water main under the railroad is complete and awaiting tie in with the remainder of the water main being installed.
• Water main work across Mayfair Rd. (STH 100) is complete and the contractor was scheduled to complete the tie in of the new main to existing mains late last week.
• Concrete restoration near Mayfair is scheduled for the week of 7/29.
• Oak Leaf Trail paving is complete. Restoration is being coordinated with Milwaukee County Parks.
• The remaining tie-ins and service laterals are anticipated to be complete by August 9th.
24-02 - 116th St. Park
• Placement of fill is on-going with sources from the Potter Road project and the Elm Grove Water Main project.
• Mass grading activities are continuing and expected to generally wrap up the week of 8/5.
• Utility work for the sanitary lateral and water service started the week of 7/22.
• Storm sewer work on-site is scheduled to follow the utilities.
• Work on the retaining wall near Walnut is scheduled to begin the week of August 5th.
24-07 - 2024 Street Improvements
• Concrete removal is complete on Sarasota Pl. and Colonial Dr.
• Pulverizing of the existing pavement was scheduled for late the week of 7/22 on Sarasota Pl. and Colonial Dr.
• Restoration behind the curb will occur following pulverizing.
• Paving on Sarasota Pl. and Colonial Dr. to follow after completion of restoration, tentatively scheduled the week of August 5th.
• Temporary electric on 115th is in place and ready for hook-up prior to storm sewer starting.
24-08 - Center St. & Discovery
• The remaining water laterals are scheduled for the week of 7/29.
• Water main work is on-going over the next couple of weeks.
• Storm sewer work is tentatively expected to start the week of 7/29 provided safe water samples on the first block of Center St. pass testing.
24-11 - Green Alleys
• Sewer work was scheduled to be installed in the alley adjacent to the 124th between Chambers/Burleigh & 122nd St. is on-going.
• Concrete placement is scheduled for the week of 7/15.
• Removals and grading in the alley north of North Avenue between Lefeber Ave and 73rd St is on-going.
• Sewer work and concrete pavement to follow in the next few weeks.
24-19 - 2024 Sidewalk Repair Program
• Sidewalk stone replacement is underway with work focused near Bluemound Rd. and portions along 124th and Burleigh.
• Work is expected to continue to work toward the north.
• Potter Rd. sidewalk is expected to be installed in around mid-August.
24-24 - Concrete Pavement Repairs
• Preconstruction meeting is scheduled for 7/29.
• Work on Capitol Dr. is expected to start late the week of 7/29.
24-51 - Mayfair Rd. Water Main Lining
• Preconstruction meeting to be scheduled for 7/30.