File #: 24-1090    Version: 1 Name:
Type: Action Item Status: Passed
File created: 7/17/2024 In control: Board of Public Works
On agenda: 7/29/2024 Final action: 7/29/2024
Title: Request by WeEnergies for Nighttime Work Hours, 7:00 P.M. to 7:00 A.M., on Wauwatosa Avenue (S.T.H. 181) - Milwaukee Avenue to Warren Avenue
Attachments: 1. 4708041 sketch_v1 (2), 2. 4708041 (1732 Wauwatosa Ave.) - Pictures

title
Request by WeEnergies for Nighttime Work Hours, 7:00 P.M. to 7:00 A.M., on Wauwatosa Avenue (S.T.H. 181) - Milwaukee Avenue to Warren Avenue

 

body

Submitted by:

Mike Steiner, Assistant City Engineer

Department:

Public Works - Engineering Division

 

A.                     Issue

Request by WeEnergies for Nighttime Work Hours, 7:00 P.M. to 7:00 A.M., on Wauwatosa Avenue (S.T.H. 181) - Milwaukee Avenue to Warren Avenue

 

 

B.                     Background/Options 

WeEnergies performed work for the Wauwatosa School District in the summer of 2023 to extend underground facilities between East High School and Lincoln Elementary School.  The approved permit sketch is attached. The work included boring across Wauwatosa Avenue.  The City requires contractors to locate existing underground utilities by coring a hole in the pavement when boring is the selected method of construction. The attached picture shows numerous cores holes in the pavement.

 

The permit required permanent restoration of the pavement upon completion.  The work was not completed last summer before school started and needs to be completed this summer. The pavement restoration required of WeEnergies includes full removal of the asphalt and concrete road base and replacement, in kind, across the entire width of Wauwatosa Avenue.  This requirement is based on the fact that the road was rebuilt in 2020.  Completion of the work will require a full closure, or flagging operations, on Wauwatosa Avenue. 

 

Staff has determined that since Wauwatosa Avenue is a connecting state highway and a main arterial, the work must be performed at night. 

 

Municipal Code Section 15.02.100 states:

1.                     No person, firm or corporation shall at any time between the hours of seven p.m. and seven a.m. Monday through Saturday, or during any hours on Sunday create any loud or sharp noises,  concussions, or disturbing sounds associated with the construction, excavation, demolition, alteration, or repair of any building or development. The board of public works may modify these times upon request for variance and based on exceptional circumstances.

WeEnergies is requesting approval for working hours between 7:00 P.M. and 7:00 A.M. on multiple nights to complete this project. WeEnergies will coordinate the actual dates for the work with the City Construction Manager prior to commencing work.

 

 

 

C.                     Strategic Plan (Area of Focus)

Infrastructure

 

 

D.                     Fiscal Impact

No impact to the City of Wauwatosa

 

 

E.                     Recommendation

Staff recommends approval of the request subject to:

1.                     Approval of selected dates by the City Construction Manager.

2.                     Applicant to provide written notices to properties within one city block of the project location, 3 days prior to work.

3.                     Reimbursement by the Applicant of the costs for public inspection services related to placement of the concrete base and asphalt roadway.