23-90 - 2023 Fiber

                     Awaiting railroad permit and work along Mayfair Rd. (City & WE Energies Gas) to clear before fiber can be pulled north.

 

23-30 - Wauwatosa Bike Share

                     Work to resume in fall in coordination with MRMC and the site work that is on-going.  Awaiting update from MRMC on status of their work.

 

Elm Grove Water Main Extension

                     Water main work in Elm Grove continues through Summer/Fall 2024.

 

24-01 - Potter Road & 109th St.

                     Water main work on Potter Rd. is complete including the key tie in to the pump station

                     Storm sewer work is on-going over the next couple weeks.

                     Work on 109th St. will take place in 2025 based on current progress on the project.

 

24-02 - 116th St. Park

                     Mass grading is complete.  Topsoil is being spread on the sledding hill.

                     All utility work is complete.

                     Concrete work and landscaping work is on-going.

                     Exterior asphalt path paving is tentatively scheduled for next week.

 

24-07 - 2024 Street Improvements

                     Concrete removal is complete on Sarasota Pl. and Colonial Dr.  

                     Landscaping was scheduled for last week and into early the week of Sept 16th on Sarasota Pl. and Colonial Dr.

                     Pulverizing of the existing pavement was scheduled for mid-week next week with the lower layer of asphalt expected early the week of 9/23.

                     Restoration behind the curb will occur following paving of the lower layer of asphalt.

                     Electrical on all three streets was scheduled to wrap up late last week.

 

24-08 - Center St. & Discovery

                     Center St. is reopened.

                     Work on Discovery Parkway has not yet started.

 

24-11 - Green Alleys

                     Substantially complete, punch list has been issued.

 

24-19 - 2024 Sidewalk Repair Program

                     Sidewalk stone replacement is work continues.

 

24-24 - Concrete Pavement Repairs

                     Wrapping up the last few alleys into early next week and then will review to issue a punch list.

 

24-51 - Mayfair Rd. Water Main Lining

                     Relay work is generally complete and water main cleaning in prep for lining is underway.

                     Lining is expected to begin the week of Sept. 23rd.