body

23-90 - 2023 Fiber

•                     Awaiting railroad permit and work along Mayfair Rd. (City & WE Energies Gas) to clear before fiber can be pulled north.

 

23-30 - Wauwatosa Bike Share

•                     Work to resume in fall in coordination with MRMC and the site work that is on-going.  Awaiting update from MRMC on status of their work.

 

Elm Grove Water Main Extension

•                     Water main work in Elm Grove continues through Summer/Fall 2024.

 

24-01 - Potter Road & 109th St.

•                     Water main work on Potter Rd. is complete including the key tie in to the pump station

•                     Storm sewer work is on-going over the next couple weeks.

•                     Work on 109th St. will take place in 2025 based on current progress on the project.

 

24-02 - 116th St. Park

•                     Mass grading is complete.  Topsoil is being spread on the sledding hill.

•                     All utility work is complete.

•                     Concrete work and landscaping work is on-going.

•                     Exterior asphalt path paving is tentatively scheduled for next week.

 

24-07 - 2024 Street Improvements

•                     Concrete removal is complete on Sarasota Pl. and Colonial Dr.  

•                     Landscaping was scheduled for last week and into early the week of Sept 16th on Sarasota Pl. and Colonial Dr.

•                     Pulverizing of the existing pavement was scheduled for mid-week next week with the lower layer of asphalt expected early the week of 9/23.

•                     Restoration behind the curb will occur following paving of the lower layer of asphalt.

•                     Electrical on all three streets was scheduled to wrap up late last week.

 

24-08 - Center St. & Discovery

•                     Center St. is reopened.

•                     Work on Discovery Parkway has not yet started.

 

24-11 - Green Alleys

•                     Substantially complete, punch list has been issued.

 

24-19 - 2024 Sidewalk Repair Program

•                     Sidewalk stone replacement is work continues.

 

24-24 - Concrete Pavement Repairs

•                     Wrapping up the last few alleys into early next week and then will review to issue a punch list.

 

24-51 - Mayfair Rd. Water Main Lining

•                     Relay work is generally complete and water main cleaning in prep for lining is underway.

•                     Lining is expected to begin the week of Sept. 23rd.