Title: Project Updates

title
Project Updates

 

body

23-90 - 2023 Fiber

                     Interior buildings walk-thru was completed. Awaiting work to be coordinated and scheduled with the facilities.

 

25-01 - Wisconsin Avenue

                     Anticipate walk work to begin in the next few weeks as weather improves.

 

25-07 - Watertown Plank Road

                     Work on driveway replacement scheduled to be complete on 116th Street early the week of 4/20.

                     Path paving to be scheduled in coordination with path paving on Watertown Plank in a couple of weeks.

                     Concrete work on Watertown Plank east of 116th is continuing through this week to be followed by path grading and paving.

                     The contractor is targeting mid-May to flip traffic on Watertown Plank east of 116th and the closure of Watertown Plank west of 116th to complete the remaining utility and road work.

 

25-07 - 2025 Sanitary Sewer Improvements (Diane Dr. & Discovery Parkway)

                     Permanent restoration is being scheduled in the next couple of weeks.

 

25-25 - Burleigh St. Path and Asphalt Repair

                     Complete - Some punch list items will carry over into Spring 2026 due to current weather conditions. Awaiting schedule based on weather.

 

26-01 - Flood Damage Maintenance Repairs

                     Original contract work is mostly complete.

                     Awaiting schedule for asphalt work in Hart Park that was added to the contract.

                     Work at 103rd Street/North Avenue on the storm sewer is scheduled for mid-May.

 

26-07 - Maple Terrace, Perry Ct, Laurel Ct.

                     Traffic control was set up last week but work start was delayed due to the weather.

                     Contractor is mobilizing in early the week of 4/20 and will begin sanitary and storm sewer work.

                     Sanitary and storm sewer work is expected to continue over the next couple of weeks.

 

26-08 - Center Street

                     Project has been awarded and the contract is in process of being executed. A preconstruction meeting will be held pending the contractor’s anticipated start date.

 

26-10 - Hart Park Restroom

                     Project has been awarded and the contract is in process of being executed. A preconstruction meeting is expected to be held in the new few weeks.

 

26-19 - Sidewalk Repair Program

                     Work is underway in Hart Park on the raised intersection crosswalks.

                     Curb ramp work is underway in the general program area for 2026.

 

Hart Park Field Repairs

                     Work is on-going. Expect completion over the next few weeks.

 

Wisconsin Avenue Bridge (WisDOT Led)

                     Spring work for restoration, masonry, and other punch list items is underway. Expected completion of this work is mid to late May.