Title: Project Updates

title
Project Updates

 

body

23-90 - 2023 Fiber

•                     Interior buildings walk-thru was completed. Awaiting work to be coordinated and scheduled with the facilities.

 

25-01 - Wisconsin Avenue

•                     Anticipate walk work to begin in the next few weeks as weather improves.

 

25-07 - Watertown Plank Road

•                     Work on driveway replacement scheduled to be complete on 116th Street early the week of 4/20.

•                     Path paving to be scheduled in coordination with path paving on Watertown Plank in a couple of weeks.

•                     Concrete work on Watertown Plank east of 116th is continuing through this week to be followed by path grading and paving.

•                     The contractor is targeting mid-May to flip traffic on Watertown Plank east of 116th and the closure of Watertown Plank west of 116th to complete the remaining utility and road work.

 

25-07 - 2025 Sanitary Sewer Improvements (Diane Dr. & Discovery Parkway)

•                     Permanent restoration is being scheduled in the next couple of weeks.

 

25-25 - Burleigh St. Path and Asphalt Repair

•                     Complete - Some punch list items will carry over into Spring 2026 due to current weather conditions. Awaiting schedule based on weather.

 

26-01 - Flood Damage Maintenance Repairs

•                     Original contract work is mostly complete.

•                     Awaiting schedule for asphalt work in Hart Park that was added to the contract.

•                     Work at 103rd Street/North Avenue on the storm sewer is scheduled for mid-May.

 

26-07 - Maple Terrace, Perry Ct, Laurel Ct.

•                     Traffic control was set up last week but work start was delayed due to the weather.

•                     Contractor is mobilizing in early the week of 4/20 and will begin sanitary and storm sewer work.

•                     Sanitary and storm sewer work is expected to continue over the next couple of weeks.

 

26-08 - Center Street

•                     Project has been awarded and the contract is in process of being executed. A preconstruction meeting will be held pending the contractor’s anticipated start date.

 

26-10 - Hart Park Restroom

•                     Project has been awarded and the contract is in process of being executed. A preconstruction meeting is expected to be held in the new few weeks.

 

26-19 - Sidewalk Repair Program

•                     Work is underway in Hart Park on the raised intersection crosswalks.

•                     Curb ramp work is underway in the general program area for 2026.

 

Hart Park Field Repairs

•                     Work is on-going. Expect completion over the next few weeks.

 

Wisconsin Avenue Bridge (WisDOT Led)

•                     Spring work for restoration, masonry, and other punch list items is underway. Expected completion of this work is mid to late May.