title
Project Updates
body
23-90 - 2023 Fiber
• Interior buildings walk-thru was completed. Awaiting work to be coordinated and scheduled with the facilities.
25-01 - Wisconsin Avenue
• Anticipate walk work to begin in the next few weeks as weather improves.
25-07 - Watertown Plank Road
• Work on driveway replacement scheduled to be complete on 116th Street early the week of 4/20.
• Path paving to be scheduled in coordination with path paving on Watertown Plank in a couple of weeks.
• Concrete work on Watertown Plank east of 116th is continuing through this week to be followed by path grading and paving.
• The contractor is targeting mid-May to flip traffic on Watertown Plank east of 116th and the closure of Watertown Plank west of 116th to complete the remaining utility and road work.
25-07 - 2025 Sanitary Sewer Improvements (Diane Dr. & Discovery Parkway)
• Permanent restoration is being scheduled in the next couple of weeks.
25-25 - Burleigh St. Path and Asphalt Repair
• Complete - Some punch list items will carry over into Spring 2026 due to current weather conditions. Awaiting schedule based on weather.
26-01 - Flood Damage Maintenance Repairs
• Original contract work is mostly complete.
• Awaiting schedule for asphalt work in Hart Park that was added to the contract.
• Work at 103rd Street/North Avenue on the storm sewer is scheduled for mid-May.
26-07 - Maple Terrace, Perry Ct, Laurel Ct.
• Traffic control was set up last week but work start was delayed due to the weather.
• Contractor is mobilizing in early the week of 4/20 and will begin sanitary and storm sewer work.
• Sanitary and storm sewer work is expected to continue over the next couple of weeks.
26-08 - Center Street
• Project has been awarded and the contract is in process of being executed. A preconstruction meeting will be held pending the contractor’s anticipated start date.
26-10 - Hart Park Restroom
• Project has been awarded and the contract is in process of being executed. A preconstruction meeting is expected to be held in the new few weeks.
26-19 - Sidewalk Repair Program
• Work is underway in Hart Park on the raised intersection crosswalks.
• Curb ramp work is underway in the general program area for 2026.
Hart Park Field Repairs
• Work is on-going. Expect completion over the next few weeks.
Wisconsin Avenue Bridge (WisDOT Led)
• Spring work for restoration, masonry, and other punch list items is underway. Expected completion of this work is mid to late May.