File #: 25-0680    Version: 1 Name:
Type: Action Item Status: Filed
File created: 4/30/2025 In control: Financial Affairs Committee
On agenda: 5/13/2025 Final action:
Title: Consideration of amendment to the 2025 Budget to reflect 2024 capital project carryovers
Attachments: 1. Capital Carryover Attachment
Related files: 25-0831

title
Consideration of amendment to the 2025 Budget to reflect 2024 capital project carryovers 

 

body

Submitted by:

John Ruggini and Thania Cervantes

Department:

Finance Department

 

A.                     Issue

Earlier this year, the 2024 Operating Carryovers were approved.   Presented here for approval are the capital project carryovers

 

 

B.                     Background/Options 

A carryover is a budgetary mechanism by which spending authority is transferred from one fiscal year to the next.  This is most often necessary where a project budgeted for in one fiscal year (2024) is not completed so that remaining committed but unspent funds associated with the project are transferred to the following fiscal year (2025).  While the City adopts a five-year capital plan, only the first year of the plan is actually authorized.  In this case, the 2024-2028 plan was adopted in December 2023 and the 2025-2029 plan was adopted in November 2024.  We are now requesting the 2025 fiscal year of the 2025-2029 plan be amended for the unspent 2024 funds.

 

Capital projects are typically complex infrastructure projects (such as street and utility construction) or large equipment purchases (such as a Fire engine) that often span multiple fiscal years so carryover funds are not uncommon.  The Capital Budget is adopted separate from the Operating budget but once approved, they are combined in the City’s financial system so spending can be tracked.  Capital projects have multiple funding sources including property taxes, special assessments, grants, surplus funds (cash) and bonds (borrowed money).  The majority of capital carryovers typically represent bond funds that have been borrowed but not yet spent.  Of the $19.6 million requested for carryover, 52% are bond funds.  These borrowed funds legally must be spent on capital projects within two years of having been borrowed. Staff actively monitor these timeliness requirements.

 

I am requesting that $19,582,958 be carried over as compared to the $16,465,418 in the prior year for previously approved capital projects.  The table below organizes the carryovers by justification:

 

Carryover Total by Justification

Amount Recommended

Annual budget rolled over

1,235,051

Future year construction

3,640,972

Project delayed

511,262

Project delayed - might repurpose funds

135,000

Project in progress

10,263,856

Project surplus - will be transferred

158,828

Punch list items

1,120,600

Vehicle being purchased in 2025

87,578

Work in 2025

2,429,811

Grand Total

19,582,958

 

 

From the perspective of an Alder, it is important to monitor delayed projects and understand the reasons for delays and any impacts on future capital budgets.  For example, often future projects are contingent on the completion of a current project.  From a staff perspective, we are often juggling limited staffing resources, changes to contingent projects that we don’t control (such as the Department of Transportation), scope changes, pricing changes or delays in land acquisition to name a few.  The table below shows which projects have been delayed.  At the meeting, staff can speak to the reasons for the delays and any potential impacts.

 

Project #

Project

Amount Recommended Carryover

8037

TENNIS COURT BATHROOM REMODEL

511,262

 

 

No new projects have been added to be funded by carryover. 

 

A full listing of all the carryovers is included as an attachment.  The majority of the projects are funded with bond proceeds which cannot be used for purposes other than capital projects and are often restricted to specific types of projects.  The Capital Budgets can be found here (<https://www.wauwatosa.net/home/showpublisheddocument/5944/638739074520430000>) if you’d like more detail on a particular project.

 

 

C.                     Strategic Plan (Area of Focus)

This carryover supports the strategic goal of maintaining city infrastructure.

 

 

 

D.                     Fiscal Impact

As all of these projects were previously budgeted, there is no fiscal impact on the 2024 Budget.

 

 

 

E.                     Recommendation

I recommend amending the 2025 Budget by increasing capital project expenditure authority up to $19,582,958 for prior year unspent funds.