title
Project Updates
body
23-90 - 2023 Fiber
• Only a few hand holes remain uninstalled.
• Still awaiting permitting through the railroad. Remaining work pending at this time as coordination continues.
• Boring work looks to start in the next week or two.
23-30 - Wauwatosa Bike Share
• Work to resume in fall in coordination with MRMC and the site work that is on-going.
Elm Grove Water Main Extension
• Water main work in Elm Grove continues through Summer/Fall 2024.
24-01 - Potter Road & 109th St.
• Water main work is underway near Mayfair Rd. and the east end of the project will continue over the next few weeks. Boring under the railroad is scheduled to begin next week.
• Lane closures are in place on Mayfair Rd. to facilitate the water main crossing from Potter Rd. to Research Dr. and expect to be in place for a couple of weeks. Lane closures will be removed the week of the 15th and resume the week of the 22nd to complete tie-ins and concrete work.
• Oak Leaf Trail paving is scheduled for the week of 7/15.
24-02 - 116th St. Park
• Placement of fill is on-going with sources from the Potter Road project and the Elm Grove Water Main project.
• Mass grading activities are will continue for the next couple of weeks.
• Utility work for the sanitary lateral and water service is scheduled to start the week of 7/22.
24-07 - 2024 Street Improvements
• Street lighting work is on-going on Sarasota Pl. and Colonial Dr.
• Concrete removal is scheduled to be complete on Sarasota Pl. by mid-week
• Colonial Dr. concrete removal and replacement began late the week of 7/8 and will continue for a couple weeks.
• Pulverizing of the pavement and paving will follow on Sarasota Pl. is scheduled for the week of 7/22 with restoration occurring in that same time frame.
• Paving on Sarasota to follow after completion of restoration.
• Temporary electric on 115th is planned to begin being installed in the next couple of weeks.
24-08 - Center St. & Discovery
• Work on the sanitary laterals are complete. Short side water laterals are complete.
• Water main work started the week of 7/8.
• Storm sewer work is expected to run concurrently with the water main in the next couple of weeks.
24-11 - Green Alleys
• Sewer work was scheduled to be installed in the alley adjacent to the 124th between Chambers/Burleigh & 122nd St. is on-going.
• Concrete placement is scheduled for the week of 7/15.
• Removals and grading in the alley north of North Avenue between Lefeber Ave and 73rd St is on-going.
• Sewer work and concrete pavement to follow in the next few weeks.
24-19 - 2024 Sidewalk Repair Program
• Sidewalk stone replacement is underway with work focused near the SW area of the City within the program limits.
24-24 - Concrete Pavement Repairs
• Preconstruction meeting to be scheduled. Date TBD.
24-51 - Mayfair Rd. Water Main Lining
• Preconstruction meeting to be scheduled. Date TBD.