title
Project Updates
body
Submitted by:
Nick Deming, Construction Manager
23-90 - 2023 Fiber
• Updating permit with DOT.
25-01 - Wisconsin Avenue
• Paving and restoration continue on Wisconsin Ave between 72nd and 68th over the next couple weeks.
• Work is complete on 70th St.
• Electrical and Signal work will also occur over the next couple of weeks.
25-07 - Watertown Plank Road
• Water main tie-ins complete
• Outfall work and box culvert work on-going
• Grading and paving in the EB lanes east of 115th St. is scheduled to start in the next couple weeks.
25-07 - 2025 Sanitary Sewer Improvements (Diane Dr. & Discovery Parkway)
• Preconstruction meeting was held on 9/9.
• Work on Diane Dr. is schedule to begin in early October.
• Work on Discovery is slated for October pending scheduling of a crew for pipe installation.
25-25 - Burleigh St. Path and Asphalt Repair
• Concrete is scheduled for the week of 9/22.
• The path is scheduled to be paved the week of 9/29.
Wisconsin Avenue Bridge (WisDOT Led)
• The abutments are near complete with work set to begin on the stream channel realignment the week of 9/22.
• Water main work is complete.
• Storm sewer work is underway.
25-11 Harvard Alley
• Alley is substantially complete.