Title: Project Updates
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title
Project Updates

 

body

Submitted by:

Nick Deming, Construction Manager

 

23-90 - 2023 Fiber

                     Updating permit with DOT.

 

25-01 - Wisconsin Avenue

                     Paving and restoration continue on Wisconsin Ave between 72nd and 68th over the next couple weeks.

                     Work is complete on 70th St.

                     Electrical and Signal work will also occur over the next couple of weeks.

 

25-07 - Watertown Plank Road

                     Water main tie-ins complete

                     Outfall work and box culvert work on-going

                     Grading and paving in the EB lanes east of 115th St. is scheduled to start in the next couple weeks.

 

25-07 - 2025 Sanitary Sewer Improvements (Diane Dr. & Discovery Parkway)

                     Preconstruction meeting was held on 9/9.

                     Work on Diane Dr. is schedule to begin in early October.

                     Work on Discovery is slated for October pending scheduling of a crew for pipe installation.

 

25-25 - Burleigh St. Path and Asphalt Repair

                     Concrete is scheduled for the week of 9/22.

                     The path is scheduled to be paved the week of 9/29.

 

Wisconsin Avenue Bridge (WisDOT Led)

                     The abutments are near complete with work set to begin on the stream channel realignment the week of 9/22.

                     Water main work is complete.

                     Storm sewer work is underway.

 

25-11 Harvard Alley

                     Alley is substantially complete.