Nick Deming, Construction Manager
Department:
Engineering
23-90 - 2023 Fiber
• Updating permit with DOT.
25-01 - Wisconsin Avenue
• Paving is complete.
• Restoration is wrapping up and punch list work is underway.
25-07 - Watertown Plank Road
• Grading for the path on 116th St. is underway.
• 115th intersection was closed and the box culvert is being installed across the intersection of 115th including the tie in across Watertown Plank.
• Grading and roadway work is also underway on the EB lanes of Watertown Plank Road between 115th Street and the railroad bridge.
25-07 - 2025 Sanitary Sewer Improvements (Diane Dr. & Discovery Parkway)
• Work on Diane Dr. is schedule to begin Monday, Oct. 20th for sanitary lateral spot repair work.
• Work is expected to begin on Discovery is early/mid November.
25-25 - Burleigh St. Path and Asphalt Repair
• Asphalt paving occurred on 10/16.
• Restoration work is set to follow paving.
Wisconsin Avenue Bridge (WisDOT Led)
• Channel realignment of the creek is wrapping up with work to start on the setting falsework and decking for the bridge deck.
• Grading and roadway work is underway on Wisconsin Avenue and Honey Creek Parkway and is expected to continue over the next few weeks.
DPW Incinerator Demolition
• The above ground portion of the building has been nearly removed.
• Concrete debris is being crushed on site.
• In the coming weeks, the below grade removal of the foundation will begin.