Title: Consideration of approval of August 2025 flood-related emergency purchases and fund transfers and update on initial assessment of public sector damage
Attachments: 1. Wauwatosa 2025 Flooding Budgetary Estimates 2025.09.19.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
Consideration of approval of August 2025 flood-related emergency purchases and fund transfers and update on initial assessment of public sector damage

body
Submitted by:
John Ruggini
Department:
Finance

A. Issue
City staff responded with emergency measures with our initial response and on-going recovery efforts to the August floods. As such, approval of emergency purchases and interim fund transfers are required.


B. Background/Options
Nearly 14 inches of rain fell over a 12-hour period from August 9-10th causing the Menomonee River to overflow its banks resulting in overland flooding. The Mayor declared an emergency and the Fire Chief activated the City's Emergency Operations Center which convened at 9:00am on Sunday, August 10th. Public Works Fire and Police departments responded to rescue residents and their pets and secure and protect public infrastructure. In accordance with emergency operation procedures, purchasing and expenditure control procedures were waived where necessary and subsequent approval is requested.

The following emergency purchases were made without competitive solicitations and require approval:
Table 1


It should be noted that the ATI Restoration company was on the state contract, so it was competitively solicited but since it is over $25,000 would have otherwise required Council approval.

In addition, fund transfers are needed in multiple departments. Initially, we are projecting the following to cover costs incurred and near future costs:

Table 2


We propose covering the General Fund and Parks costs from the General Fund Unassigned Reserve and the other funds from their own fund balances. These amounts could be reimbursed in the future when a FEMA determination has been made. In the meantime, we are expecting the following insurance reimbursements and recommend fund transfers to recognize the revenue (* indicates estimates not yet approved):

Table 3


The City was also fortunate to receive a $1,000,000 ...