Title: Project Updates

title
Project Updates

 

body

 

23-90 - 2023 Fiber

•                     The contractor is looking to start pulling fiber in the next few weeks once the WisDOT permit extension is received.

 

Elm Grove Water Main Extension

•                     Additional lateral work is on-going and expected to wrap up in the next few weeks.

 

24-01 - Potter Road & 109th St.

•                     Storm sewer work continues.

•                     Street work is expected to begin in the next couple of weeks.

 

24-02 - 116th St. Park

•                     Work on the retaining wall on the south end of the project is nearly complete.

•                     Paving of the paths is complete

•                     Restoration is on-going throughout the site area.

•                     Final prep continues with an expected opening of the park in late May.

 

25-01 - Wisconsin Avenue

•                     Sanitary work is on-going and expected to continue for another week or so.

•                     Storm sewer work started and will continue for the next few weeks.

 

25-07 - Watertown Plank Road

•                     Tree Clearing on county grounds is complete. The trees felled earlier have been cleared.

•                     Traffic was switched on Watertown Plank Road and work on the water main will continue over the next couple of weeks.

 

25-08 - Center Street

•                     A preconstruction meeting will be scheduled upon execution of the contract.

 

25-19 - 2025 Sidewalk Program

•                     Sidewalk work is expected to begin the week of 5/19.

 

Wisconsin Avenue Bridge (WisDOT Led)

•                     Bridge demolition is underway and will be followed by construction of the bridge abutments.