title
Project Updates
body
23-90 - 2023 Fiber
• The contractor is looking to start pulling fiber in the next few weeks once the WisDOT permit extension is received.
Elm Grove Water Main Extension
• Additional lateral work is on-going and expected to wrap up in the next few weeks.
24-01 - Potter Road & 109th St.
• Storm sewer work continues.
• Street work is expected to begin in the next couple of weeks.
24-02 - 116th St. Park
• Work on the retaining wall on the south end of the project is nearly complete.
• Paving of the paths is complete
• Restoration is on-going throughout the site area.
• Final prep continues with an expected opening of the park in late May.
25-01 - Wisconsin Avenue
• Sanitary work is on-going and expected to continue for another week or so.
• Storm sewer work started and will continue for the next few weeks.
25-07 - Watertown Plank Road
• Tree Clearing on county grounds is complete. The trees felled earlier have been cleared.
• Traffic was switched on Watertown Plank Road and work on the water main will continue over the next couple of weeks.
25-08 - Center Street
• A preconstruction meeting will be scheduled upon execution of the contract.
25-19 - 2025 Sidewalk Program
• Sidewalk work is expected to begin the week of 5/19.
Wisconsin Avenue Bridge (WisDOT Led)
• Bridge demolition is underway and will be followed by construction of the bridge abutments.