Skip to main content
File #: 25-0747    Version: 1 Name:
Type: Report Status: Information Only
File created: 5/7/2025 In control: Board of Public Works
On agenda: 5/14/2025 Final action: 5/14/2025
Title: Project Updates

title
Project Updates

 

body

 

23-90 - 2023 Fiber

                     The contractor is looking to start pulling fiber in the next few weeks once the WisDOT permit extension is received.

 

Elm Grove Water Main Extension

                     Additional lateral work is on-going and expected to wrap up in the next few weeks.

 

24-01 - Potter Road & 109th St.

                     Storm sewer work continues.

                     Street work is expected to begin in the next couple of weeks.

 

24-02 - 116th St. Park

                     Work on the retaining wall on the south end of the project is nearly complete.

                     Paving of the paths is complete

                     Restoration is on-going throughout the site area.

                     Final prep continues with an expected opening of the park in late May.

 

25-01 - Wisconsin Avenue

                     Sanitary work is on-going and expected to continue for another week or so.

                     Storm sewer work started and will continue for the next few weeks.

 

25-07 - Watertown Plank Road

                     Tree Clearing on county grounds is complete. The trees felled earlier have been cleared.

                     Traffic was switched on Watertown Plank Road and work on the water main will continue over the next couple of weeks.

 

25-08 - Center Street

                     A preconstruction meeting will be scheduled upon execution of the contract.

 

25-19 - 2025 Sidewalk Program

                     Sidewalk work is expected to begin the week of 5/19.

 

Wisconsin Avenue Bridge (WisDOT Led)

                     Bridge demolition is underway and will be followed by construction of the bridge abutments.