Skip to main content
File #: 23-1023    Version: 1 Name:
Type: Report Status: Information Only
File created: 4/28/2023 In control: Board of Public Works
On agenda: 5/1/2023 Final action: 5/1/2023
Title: Project Updates

title
Project Updates

 

body

Submitted by:

Nicholas Deming

Department:

Engineering Division

 

21-47/48 Zoo Interchange North Leg (WisDOT Project)

                     Work and lane closures continue at the freeway overpasses at North Avenue and Mayfair Road to accommodate work overhead on the freeway structures.

                     The contractor has closed a lane on WB North Avenue to facilitate their work.  This is expected to continue to remain one lane thru 114th St. thru late May/Early June.

                     Work is expected to start on pavement on the North Avenue Ramps to and from NB I41/USH45.

 

22-05 - 103rd St. Storm Sewer Relay

                     Contractor working on restoration around the properties on the south end of the project near North Ave and installing catch basins and leads. 

                     The contractor anticipates starting to receive the 5x6 box culvert sections the week of May 1st to continue north with the storm sewer relay on 103rd St.

 

22-08 - N 68th St.

                     A punch list is being developed for the contractor for 68th St.

                     Street lighting work is being coordinated with WE Energies for the cabinet replacement around 66th & Cedar.

 

22-60 - DPW Garage Floor Drain Reconstruction

                     The resinous flooring is installed and the project is substantially complete.

 

Project 1107 - North Avenue Reconstruction

                     The contractor shifted traffic on Tuesday, 4/25 into Stage 1.

                     The contractor is intending to start water main work late the week of April 24th near Mayfair Rd and work to the east.

                     The contractor is intending on bringing in a second crew to follow the water main crew with the storm sewer installation the week of May 1st.

 

23-19 - 2023 Sidewalk Program

                     Remarking of sidewalk is complete and letters were sent to residents on April 14th.

                     Work is expected to start in early to mid-May.