Title: Project Updates

title
Project Updates

 

body

Submitted by:

Nicholas Deming

Department:

Engineering Division

 

21-47/48 Zoo Interchange North Leg (WisDOT Project)

•                     Work and lane closures continue at the freeway overpasses at North Avenue and Mayfair Road to accommodate work overhead on the freeway structures.

•                     The contractor has closed a lane on WB North Avenue to facilitate their work.  This is expected to continue to remain one lane thru 114th St. thru late May/Early June.

•                     Work is expected to start on pavement on the North Avenue Ramps to and from NB I41/USH45.

 

22-05 - 103rd St. Storm Sewer Relay

•                     Contractor working on restoration around the properties on the south end of the project near North Ave and installing catch basins and leads. 

•                     The contractor anticipates starting to receive the 5x6 box culvert sections the week of May 1st to continue north with the storm sewer relay on 103rd St.

 

22-08 - N 68th St.

•                     A punch list is being developed for the contractor for 68th St.

•                     Street lighting work is being coordinated with WE Energies for the cabinet replacement around 66th & Cedar.

 

22-60 - DPW Garage Floor Drain Reconstruction

•                     The resinous flooring is installed and the project is substantially complete.

 

Project 1107 - North Avenue Reconstruction

•                     The contractor shifted traffic on Tuesday, 4/25 into Stage 1.

•                     The contractor is intending to start water main work late the week of April 24th near Mayfair Rd and work to the east.

•                     The contractor is intending on bringing in a second crew to follow the water main crew with the storm sewer installation the week of May 1st.

 

23-19 - 2023 Sidewalk Program

•                     Remarking of sidewalk is complete and letters were sent to residents on April 14th.

•                     Work is expected to start in early to mid-May.