title
Project Updates
body
Submitted by:
Nicholas Deming
Department:
Engineering Division
21-47/48 Zoo Interchange North Leg (WisDOT Project)
• Work on the freeway continues with various impacts for access and construction on Mayfair Rd for bridge work.
• Most work on along North Avenue (including adjacent streets), 112th & 113th is complete.
• The North Leg landscaping contract has a preconstruction meeting scheduled for 2/7 which is scheduled to complete the remaining final restoration along North Avenue (including adjacent streets), 112th & 113th this spring/early summer.
22-05 - 103rd St. Storm Sewer Relay
• Work is starting possibly March 2nd/3rd with preliminary work.
• Additional preliminary work will be completed the week of March 6th with work continuing to ramp up over the next couple weeks.
22-08 - N 68th St.
• Electrical work is pending the arrival of specific materials. The contractor intends to begin installation of these materials once available.
22-60 - DPW Garage Floor Drain Reconstruction
• The resinous flooring in the wash bay is scheduled for installation in April, 2023 when wash out of various vehicles can take place outside until the resinous floor is complete.