Title: Project Updates

title
Project Updates

 

body

Submitted by:

Nicholas Deming

Department:

Engineering Division

 

21-47/48 Zoo Interchange North Leg (WisDOT Project)

                     Work on the freeway continues with various impacts for access and construction on Mayfair Rd for bridge work.

                     Most work on along North Avenue (including adjacent streets), 112th & 113th is complete.

                     The North Leg landscaping contract has a preconstruction meeting scheduled for 2/7 which is scheduled to complete the remaining final restoration along North Avenue (including adjacent streets), 112th & 113th this spring/early summer.

 

22-05 - 103rd St. Storm Sewer Relay

                     Work is starting possibly March 2nd/3rd with preliminary work.

                     Additional preliminary work will be completed the week of March 6th with work continuing to ramp up over the next couple weeks.

 

22-08 - N 68th St.

                     Electrical work is pending the arrival of specific materials.  The contractor intends to begin installation of these materials once available.

 

22-60 - DPW Garage Floor Drain Reconstruction

                     The resinous flooring in the wash bay is scheduled for installation in April, 2023 when wash out of various vehicles can take place outside until the resinous floor is complete.