File #: 23-624    Version: 1 Name:
Type: Action Item Status: Passed
File created: 8/31/2023 In control: Board of Public Works
On agenda: 9/5/2023 Final action: 9/5/2023
Title: Consideration of approval of overnight work for a water main connection on Watertown Plank Road at 118th Street
Attachments: 1. Area of Work

title
Consideration of approval of overnight work for a water main connection on Watertown Plank Road at 118th Street

 

body

A.                     Issue

A request has been made to work overnight near the intersection of 118th Street and Watertown Plank Road.

 

 

B.                     Background/Options 

DF Tomasini is relaying watermain on Watertown Plank Rd. as part of the extension of water main to serve a portion of Elm Grove. As part of this work, a connection to the existing water main needs to be made which requires shutting down the one of the main water main feeds supplying the western zone of the City.  Due to the high impact of the shutdown, the connection requires working overnight from 7pm to 5am when demand on the water system is lower than daytime high demand periods.  DF Tomasini is requesting to have this overnight work approved by the board in order to make this connection on Watertown Plank Road near 118th St. during the overnight period on Thursday night September 7th beginning at 7pm thru Friday morning September 8th at 5am.

 

 

C.                     Strategic Plan (Area of Focus)

Infrastructure.

 

 

D.                     Fiscal Impact

None.

 

 

E.                     Recommendation

Allow overnight work to be completed by DF Tomasini Thursday night September 7th beginning at 7pm thru Friday morning September 8th at 5am.