File #: 25-1676    Version: 1 Name:
Type: Resolution-Council Status: Passed
File created: 9/24/2025 In control: Common Council
On agenda: 9/30/2025 Final action: 9/30/2025
Title: Resolution approving Change Order #02 for Contract 25-19, 2025 Sidewalk Repair Program
Attachments: 1. R-25-144 - Approving Change Order 02 for Contract 25-19, 2025 Sidewalk Repair Program
Related files: 25-1612

title
Resolution approving Change Order #02 for Contract 25-19, 2025 Sidewalk Repair Program

 

body

WHEREAS, the Board of Public Works is requesting a change order to Contract 25-19 to add scope items to install a new curb bump out and two pedestrian ramps in the northeast corner of Wauwatosa Avenue and Wright Street;

 

WHEREAS, the estimated total cost of the scope changes within Change Order #02 is $39,658.11;

 

NOW, THEREFORE, BE IT RESOLVED by the Common Council of the City of Wauwatosa that a change order for additional work to install a new curb bump out and two pedestrian ramps in the northeast corner of Wauwatosa Avenue and Wright Street be approved as part of Contract 25-19.

 

 

 

By: Board of Public Works

 

recommendation

Recommendation: Approved 4-0