Skip to main content
File #: 25-0665    Version: 1 Name:
Type: Resolution-Council Status: Passed
File created: 4/16/2025 In control: Common Council
On agenda: 4/22/2025 Final action: 4/22/2025
Title: Resolution approving the Final Payment for Contract 24-11 2024 Alley Reconstruction
Attachments: 1. R-25-57 - Approving Final Payment for Contract 24-11 2024 Alley Reconstruction
Related files: 25-0616

title
Resolution approving the Final Payment for Contract 24-11 2024 Alley Reconstruction

 

body

WHEREAS, the Board of Public Works has accepted the work of LaLonde Contractors, Inc.,  and work incidental thereto in the City of Wauwatosa under Contract 24-11, 2024 Alley Reconstruction and the same is ready for final payment.

 

NOW, THEREFORE, BE IT RESOLVED by the Common Council of the City of Wauwatosa, Wisconsin as follows:

 

Section 1.  That the work of LaLonde Contractors, Inc. under Contract 24-11 is hereby accepted; and

                     

Section 2. That the proper City officers be and they are hereby authorized and directed to draw and sign a City order in the sum of $8, 578.12 as the final payment under said contract, upon receipt of waivers of lien and for labor and materials furnished under said contract.

 

 

 

By: Board of Public Works

 

recommendation

Recommendation: Approve 6-0