File #: 26-0336    Version: 1 Name:
Type: Action Item Status: Passed
File created: 2/9/2026 In control: Board of Public Works
On agenda: 2/18/2026 Final action:
Title: Recommendation of Award of Contract 26-07 / Project 1026, 2026 Street & Utility Improvements to Globe Contractors, Inc. in the amount of $2,007,727.00. Project limits include Perry Court, Laurel Court, and Maple Terrace from 76th Street to 75th Street
Attachments: 1. 26-07 Award Resolution.pdf

title
Recommendation of Award of Contract 26-07 / Project 1026, 2026 Street & Utility Improvements to Globe Contractors, Inc. in the amount of $2,007,727.00. Project limits include Perry Court, Laurel Court, and Maple Terrace from 76
th Street to 75th Street

 

body

Submitted by:

Jessica Henderson, P.E., Civil Engineer

Department:

Public Works, Engineering Division

 

A.                     Issue

Consideration of award of Contract 26-07 / Project 1026, 2026 Street & Utility Improvements, to Globe Contractors, Inc. in the amount of $2,007,727.00. Project limits include Perry Court, Laurel Court, and Maple Terrace from 76th Street to 75th Street.

 

B.                     Background/Options 

The project consists of sanitary sewer, water main, storm sewer, asphalt repaving and reconstruction, concrete curb and gutter replacement, ADA curb ramps and street lighting improvements within the project limits.  Project limits include Perry Court, Laurel Court, and Maple Terrace from 76th Street to 75th Street. The work is planned for the 2026 construction season.  

We have examined the three (3) bids submitted for 26-07 / Project 1026, 2026 Street & Utility Improvements on Wednesday, February 11, 2026.  The bids received are as follows:

 

Globe Contractors, Inc.                                                               $2,007,727.00

Mid City Corporation                                                               $2,208,909.55

LaLonde Contractors Inc.                                          $2,423,230.06

 

C.                     Strategic Plan (Area of Focus)

Priority 3: Infrastructure, Goal 1 - Optimize infrastructure to handle 100-year storm events.

 

D.                     Fiscal Impact

Project 1026 is included in the approved 2026-2030 Capital Budget.

 

 

E.                     Recommendation

Staff recommends the award be made to Globe Contractors, Inc. and for their bid price of $2,007,727.00, this being the lowest and best bid.

 

recommendation

Recommendation: Common Council