titleApproval of Final Payment for Contract 25-21 / Project 2307, Swan Boulevard Bridge Deck Sealing
body
Dear Board Members:
Fahrner Asphalt Sealers, LLC has completed the work of sealing the Swan Boulevard Bridge Deck and work incidental thereto under Contract 25-21 / Project 2307.
The final contract value and amount due to the contractor is $43,024.80. The contract award amount was $43,024.80
I hereby certify that the work on Contract 25-21 / Project 2307 was completed in a manner satisfactory to the City of Wauwatosa and recommend acceptance of the same by the Board of Public Works.
Sincerely,
Jessica Henderson, P.E.
Civil Engineer II
recommendation
Recommendation: Common Council