Legislation Details

File #: 26-0745    Version: Name:
Type: Action Item Status: Agenda Ready
File created: 4/13/2026 In control: Board of Public Works
On agenda: 4/22/2026 Final action:
Title: Consideration of award of Contract 26-11 / Project 10262, 2026 Green Alley to All-Ways Contractors, Inc.
Attachments: 1. 26-11 Award Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title
Consideration of award of Contract 26-11 / Project 10262, 2026 Green Alley to All-Ways Contractors, Inc.

body

Submitted by:

Valeria Breimon-Flores, Civil Engineer

Department:

Public Works, Engineering Division

A.                     Issue

Consideration of award of Contract 26-11 / Project 10262, 2026 Green Alley to All-Ways Contractors, Inc. in the amount of $307,635.55.

 

 

B.                     Background/Options 

The project consists of green alley construction including permeable pavers, storm sewer underdrain installation, and storm sewer lining within project limits. Project limits are the alley from Mayfair Rd to 102nd St, between North Ave and Beverly Pl. The work is planned for the 2026 construction season.  

 

We have examined the 2 bids submitted for Contract 26-11 / Project 10262, 2026 Green Alley on Wednesday, April 15, 2026. The bids received are as follows:

 

All-Ways Contractors, Inc.                                                                                    $307,635.55

LaLonde Contractors, Inc.                                                                                    $319,609.11

 

 

C.                     Strategic Plan (Area of Focus)

Priority Area Three: Infrastructure

 

 

D.                     Fiscal Impact

Project 10262 is included in the approved 2026-2031 Capital Budget.

 

 

E.                     Recommendation

Staff recommends the award be made to All-Ways Contractors, Inc. for their bid price of $307,635.55, this being the lowest and best bid.

 

 