Title: Project Updates

title
Project Updates

 

body

Submitted by:

Nick Deming, Construction Manager

Department:

Engineering

 

Project 1107 - North Avenue Reconstruction

                     Punch list work and final landscaping to resume in spring.

 

23-07 - 115th St.

                     Installation of the remaining electrical items delayed due to the lead time on light poles is on-going.  Final restoration around the electrical items will take place in the spring.

 

23-90 - 2023 Fiber

                     Work is expected to resume in spring.  Some handhole installation work may take places as weather allows through the winter.

 

Elm Grove Water Main Extension

                     The remaining water main work is expected to resume in early-mid March.

 

24-01 - Potter Road & 109th St.

                     The Preconstruction Meeting is scheduled for 10am on 2/28.

                     Work is expected to begin in early-mid March.