title
Project Updates
body
Submitted by:
Nicholas Deming
Department:
Engineering Division
21-47/48 Zoo Interchange North Leg (WisDOT Project)
• Work and lane closures continue at the freeway overpasses at North Avenue and Mayfair Road.
• Overnight work is expected to take place in the next few weeks to facilitate girder installation. Other work is being coordinated with the overnight closures during girder installation.
22-05 - 103rd St. Storm Sewer Relay
• Contractor is working on installing water service laterals and relaying sanitary sewer laterals in conflict with the proposed storm sewer. They anticipate wrapping most of this work up late the week of 3/27.
• The week of 4/3, the contractor is planning to start prepping to install storm sewer starting nearest North Avenue. The first portion (~275’) is within the easement between properties and is expected to continue over the next several weeks.
22-08 - N 68th St.
• Electrical work is on-going. The contractor is intending to have the signals active in the next couple of weeks.
• Once the signal work is completed, the contractor intends to start working on installing the decorative street lighting in the area of 68th & Wells.
22-60 - DPW Garage Floor Drain Reconstruction
• The resinous flooring in the wash bay is scheduled for installation in April, 2023 when wash out of various vehicles can take place outside until the resinous floor is complete.
Project 1107 - North Avenue Reconstruction
• The contract has been executed with Vinton Construction.
• An information meeting and preconstruction meeting are tentatively being scheduled for the week of April 10th.
• Work is expected to start in the next few weeks.
23-19 - 2023 Sidewalk Program
Remarking of sidewalk prior to letters to residents going out is on-going.
A preconstruction meeting was held on 3/20. Work is expected to start on the program in mid-late April.