Skip to main content
File #: 23-999    Version: 1 Name:
Type: Report Status: Information Only
File created: 4/14/2023 In control: Design Review Board
On agenda: 4/17/2023 Final action: 4/17/2023
Title: Project Updates

title
Project Updates

 

body

Submitted by:

Nicholas Deming

Department:

Engineering Division

 

21-47/48 Zoo Interchange North Leg (WisDOT Project)

                     Work and lane closures continue at the freeway overpasses at North Avenue and Mayfair Road to accommodate work overhead on the freeway structures.

                     Overnight work is continuing over the next week for demolition of the I-41 SB structures over North Avenue.

 

22-05 - 103rd St. Storm Sewer Relay

                     Contractor is installing the box culvert.  They anticipate clearing the area within the easement between North Avenue and Beverly St. the end of the week of April 10th.

                     The contractor anticipates shifting to other work on-site while waiting for the 5x6 box to be delivered.

 

22-08 - N 68th St.

                     Electrical work is complete with the new signals online.

                     Concrete work is complete with a punch list walk to follow in the near future.

                     Street lighting work is being coordinated with WE Energies for the cabinet replacement around 66th & Cedar.

 

22-60 - DPW Garage Floor Drain Reconstruction

                     The resinous flooring in the wash bay is scheduled for installation in April 17th, 2023 and is expected to take about 1 week.

 

Project 1107 - North Avenue Reconstruction

                     The information meeting and precon meeting were held the week of the 10th.

                     Traffic was expected to be shifted to allow the pre-stage work to start on Friday, 4/14.

                     The contractor has started preliminary work and is expecting to get a full notice to proceed from the Department early the week of the 17th.

                     The contractor expected to shift all traffic to the north half of the North Avenue early the week of April 24th.

 

23-19 - 2023 Sidewalk Program

                     Remarking of sidewalk prior to letters to residents going out is on-going.

                     A preconstruction meeting was held on 3/20.  Work is expected to start on the program in late April or early May.