Title: Project Updates

title
Project Updates

 

body

Submitted by:

Nicholas Deming

Department:

Engineering Division

 

21-47/48 Zoo Interchange North Leg (WisDOT Project)

•                     Work and lane closures continue at the freeway overpasses at North Avenue and Mayfair Road to accommodate work overhead on the freeway structures.

•                     Overnight work is continuing over the next week for demolition of the I-41 SB structures over North Avenue.

 

22-05 - 103rd St. Storm Sewer Relay

•                     Contractor is installing the box culvert.  They anticipate clearing the area within the easement between North Avenue and Beverly St. the end of the week of April 10th.

•                     The contractor anticipates shifting to other work on-site while waiting for the 5x6 box to be delivered.

 

22-08 - N 68th St.

•                     Electrical work is complete with the new signals online.

•                     Concrete work is complete with a punch list walk to follow in the near future.

•                     Street lighting work is being coordinated with WE Energies for the cabinet replacement around 66th & Cedar.

 

22-60 - DPW Garage Floor Drain Reconstruction

•                     The resinous flooring in the wash bay is scheduled for installation in April 17th, 2023 and is expected to take about 1 week.

 

Project 1107 - North Avenue Reconstruction

•                     The information meeting and precon meeting were held the week of the 10th.

•                     Traffic was expected to be shifted to allow the pre-stage work to start on Friday, 4/14.

•                     The contractor has started preliminary work and is expecting to get a full notice to proceed from the Department early the week of the 17th.

•                     The contractor expected to shift all traffic to the north half of the North Avenue early the week of April 24th.

 

23-19 - 2023 Sidewalk Program

•                     Remarking of sidewalk prior to letters to residents going out is on-going.

•                     A preconstruction meeting was held on 3/20.  Work is expected to start on the program in late April or early May.