File #: 25-1561    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 9/15/2025 In control: Financial Affairs Committee
On agenda: 9/23/2025 Final action:
Title: Consideration of request by Facilities Manager for approval of final invoice payment to Statz Restoration for bathroom remodel construction, exceeding the original contract amount by $17,580
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title
Consideration of request by Facilities Manager for approval of final invoice payment to Statz Restoration for bathroom remodel construction, exceeding the original contract amount by $17,580

 

body

Submitted by:

Charles Pomerenke, Facilities Manager

Department:

Public Works

 

A.                     Issue

During the renovation of the lower level restrooms in City Hall, the contractor, Statz Restorations, over spent on their scope of work in the amount of $17,580 without prior approval from the City.

 

 

B.                     Background/Options 

Statz Restorations, a pre-qualified vendor, was issued a Purchase Order (PO) in the amount of $24,900 to complete certain tasks in the renovation of the lower level restrooms in City Hall.  During the construction process, some unforeseen conditions were discovered that affected their scope of work and the contractor under estimated the labor hours required to complete the work. This resulted in the contractor incurring costs in excess of the approved PO, and the work was nearly complete when the contractor brought this to staff’s attention. Because the extra work brought the total costs over $25,000, Common Council approval is needed in order to pay the overage.  Statz Restorations has submitted an invoice for the amount over the original PO amount and I believe that the invoice accurately reflects their incurred costs.

 

 

C.                     Strategic Plan (Area of Focus)

Well-maintained City infrastructure.

 

 

D.                     Fiscal Impact

None.  This work was completed within the total project budget, even with this overage.

 

 

E.                     Recommendation

Staff recommends approving the payment to Statz Restorations for the work completed and invoiced for a total cost of $42,480.