title
Approval of Final Payment for Contract 24-11 2024 Alley Reconstruction
body
Submitted by:
Nick Deming, Construction Manager
Department:
Engineering
Dear Board Members:
LaLonde Contractors Inc. has completed the work of the 2024 Alleys and Pavement Repairs project and work incidental thereto under Contract 24-11 / Project 1023. The work took place on the alleys at N 122nd to 124th St. from Chambers St. to Burleigh St., N 73rd to Lefeber Ave. from North Ave. to Meinecke Ave. As well as the N 124th St. pedestrian ramps at Chambers St., Locust St., and Hadley St.
The final contract value due to the contractor is $702,080.29. The contract award amount was $699,031.59. The final amount due the contractor is $49,946.03. The final contract value was $3,048.70 over the contract award amount due to standard overruns and underruns of contract quantities.
I hereby certify that the work on Contract 24-11 / Project 1023 was completed in a manner satisfactory to the City of Wauwatosa and recommend acceptance of the same by the Board of Public Works.
Sincerely,
Nick Deming
recommendation
Recommendation: Common Council