WHEREAS, the Engineering Department is seeking to purchase materials that are expected to be available after the completion date if not ordered in advance;
WHEREAS, there are three projects that are anticipated to be impacted and the materials needed include water main valves and fittings, signal poles and bases and street light poles and the Engineering Department is seeking the approval of $1,000,000.00 budgeted in 2025 to procure long lead time materials;
NOW THEREFORE BE IT RESOLVED by the Common Council of the City of Wauwatosa that the expenditure of funds requested by the Engineering Department for advance purchase of materials for certain 2025 Capital Improvements Program projects, as described at the Financial Affairs meeting on October 15, 2024, be approved.
By: Financial Affairs Committee
recommendation
Recommendation: Approve 8-0