Project Updates

 

body

23-90 - 2023 Fiber

                     Railroad flagging for the bore shot on 115th St. is scheduled in early January. Work was started last week.

                     Work was started on finishing conduit and handhole installation within WisDOT right of way.

 

Elm Grove Water Main Extension

                     The remaining water main has been dedicated to the City of Wauwatosa

                     Additional lateral work will resume once weather is favorable in the spring of 2025.

 

24-01 - Potter Road & 109th St.

                     Work on 109th St. will take place in 2025 based on current progress on the project.

 

24-02 - 116th St. Park

                     Work on the retaining wall on the south end of the project is ongoing.