23-90 - 2023 Fiber

•                     Railroad flagging for the bore shot on 115th St. is scheduled in early January. Work was started last week.

•                     Work was started on finishing conduit and handhole installation within WisDOT right of way.

 

Elm Grove Water Main Extension

•                     The remaining water main has been dedicated to the City of Wauwatosa

•                     Additional lateral work will resume once weather is favorable in the spring of 2025.

 

24-01 - Potter Road & 109th St.

•                     Work on 109th St. will take place in 2025 based on current progress on the project.

 

24-02 - 116th St. Park

•                     Work on the retaining wall on the south end of the project is ongoing.