21-47/48 Zoo Interchange North Leg (WisDOT Project)

•                     Work and lane closures continue at the freeway overpasses at North Avenue and Mayfair Road to accommodate work overhead on the freeway structures.

•                     Night work is planned to take place the week of the 5th and the night of Sept 11th to switch traffic on the freeway.

•                     The contractor will have North Avenue reduced to a single lane in each direction and is anticipated to remain in place thru late 2023 near the freeway to facilitate construction of the new overpasses.

 

22-05 - 103rd St. Storm Sewer Relay

•                     Restoration work complete and watering to establish grass is on-going.

 

Project 1107 - North Avenue Reconstruction

•                     Traffic was switched to the south side of North Avenue in full the week of Aug 28th.

•                     Underground utility work (Water, Storm & Sanitary) is on-going on the north side of North Avenue.

•                     Grading work is scheduled to start the week of Sept. 5th beginning with the east end of the project.

 

23-07 - 115th St.

•                     Storm sewer work is complete.

•                     Binder was placed last week.

•                     Underground electrical is complete.  Due to material lead times with concrete light poles, the temporary lighting will remain in place until the poles arrive and the electrical can be completed.

•                     Inlet and MH adjustments are being scheduled so the remainder of the curb can be patched in and the roadway surface completed.

 

23-19 - 2023 Sidewalk Program

•                     Substantially Complete.

 

23-24 - 2023 Pavement Repair and Spot Improvements

•                     Work is scheduled to start on 9/5 at Menomonee River Parkway installing the first portion of sidewalk

•                     Once complete, work in the remainder of the intersection improvements and the crossing at Sendiks is planned to immediately follow.

 

23-90 - 2023 Fiber

•                     Contracts are executed.

•                     Precon to be scheduled.