Title: Project Updates

title

Project Updates

end

body

21-47/48 Zoo Interchange North Leg (WisDOT Project)

                     Work and lane closures continue at the freeway overpasses at North Avenue and Mayfair Road to accommodate work overhead on the freeway structures.

                     Night work is planned to take place the week of the 5th and the night of Sept 11th to switch traffic on the freeway.

                     The contractor will have North Avenue reduced to a single lane in each direction and is anticipated to remain in place thru late 2023 near the freeway to facilitate construction of the new overpasses.

 

22-05 - 103rd St. Storm Sewer Relay

                     Restoration work complete and watering to establish grass is on-going.

 

Project 1107 - North Avenue Reconstruction

                     Traffic was switched to the south side of North Avenue in full the week of Aug 28th.

                     Underground utility work (Water, Storm & Sanitary) is on-going on the north side of North Avenue.

                     Grading work is scheduled to start the week of Sept. 5th beginning with the east end of the project.

 

23-07 - 115th St.

                     Storm sewer work is complete.

                     Binder was placed last week.

                     Underground electrical is complete.  Due to material lead times with concrete light poles, the temporary lighting will remain in place until the poles arrive and the electrical can be completed.

                     Inlet and MH adjustments are being scheduled so the remainder of the curb can be patched in and the roadway surface completed.

 

23-19 - 2023 Sidewalk Program

                     Substantially Complete.

 

23-24 - 2023 Pavement Repair and Spot Improvements

                     Work is scheduled to start on 9/5 at Menomonee River Parkway installing the first portion of sidewalk

                     Once complete, work in the remainder of the intersection improvements and the crossing at Sendiks is planned to immediately follow.

 

23-90 - 2023 Fiber

                     Contracts are executed.

                     Precon to be scheduled.