21-47/48 Zoo Interchange North Leg (WisDOT Project)
• Work and lane closures continue at the freeway overpasses at North Avenue and Mayfair Road to accommodate work overhead on the freeway structures.
• Night work is planned to take place the week of the 5th and the night of Sept 11th to switch traffic on the freeway.
• The contractor will have North Avenue reduced to a single lane in each direction and is anticipated to remain in place thru late 2023 near the freeway to facilitate construction of the new overpasses.
22-05 - 103rd St. Storm Sewer Relay
• Restoration work complete and watering to establish grass is on-going.
Project 1107 - North Avenue Reconstruction
• Traffic was switched to the south side of North Avenue in full the week of Aug 28th.
• Underground utility work (Water, Storm & Sanitary) is on-going on the north side of North Avenue.
• Grading work is scheduled to start the week of Sept. 5th beginning with the east end of the project.
23-07 - 115th St.
• Storm sewer work is complete.
• Binder was placed last week.
• Underground electrical is complete. Due to material lead times with concrete light poles, the temporary lighting will remain in place until the poles arrive and the electrical can be completed.
• Inlet and MH adjustments are being scheduled so the remainder of the curb can be patched in and the roadway surface completed.
23-19 - 2023 Sidewalk Program
• Substantially Complete.
23-24 - 2023 Pavement Repair and Spot Improvements
• Work is scheduled to start on 9/5 at Menomonee River Parkway installing the first portion of sidewalk
• Once complete, work in the remainder of the intersection improvements and the crossing at Sendiks is planned to immediately follow.
23-90 - 2023 Fiber
• Contracts are executed.
• Precon to be scheduled.