Skip to main content
File #: 24-0120    Version: 1 Name:
Type: Action Item Status: Passed
File created: 1/22/2024 In control: Transportation Affairs Committee
On agenda: 1/30/2024 Final action: 1/30/2024
Title: Consideration of a request from the Engineering Division to approve conceptual parking restrictions on Watertown Plank Road from 124th Street to approximately 725-feet east of 113th Street and on 115th Street from Watertown Plank Road to Underwood Parkway as part of Year 2025 Watertown Plank Road and 115th Street pavement projects to control traffic speeds and to provide enhanced bicycle and pedestrian accommodations and safety
Sponsors: Engineering
Indexes: Parking
Attachments: 1. WTP & 115th Pavement Project Limits, 2. Preliminary Concept Drawing - WTP - 2024-01-26, 3. Prelminary Concept Drawing - 115th - 2024-01-26, 4. Existing vs Conceptual Parking Restrictions - 2024-01-26, 5. Combined Public Comment, 6. ecomments_export
title
Consideration of a request from the Engineering Division to approve conceptual parking restrictions on Watertown Plank Road from 124th Street to approximately 725-feet east of 113th Street and on 115th Street from Watertown Plank Road to Underwood Parkway as part of Year 2025 Watertown Plank Road and 115th Street pavement projects to control traffic speeds and to provide enhanced bicycle and pedestrian accommodations and safety

body
Submitted by:
Michael May, PE, PTOE, RSP1

Department:
DPW-Engineering

A. Issue
The preliminary conceptual design for the Year 2025 Watertown Plank Road and 115th Street pavement projects necessitates modifying parking on Watertown Plank Road from 124th Street to approximately 725-feet east of 113th Street and on 115th Street from Watertown Plank Road to Underwood Parkway.


B. Background/Options
The Year 2025 Watertown Plank Road pavement project extends from 124th Street to approximately 725-feet east of 113th Street. The CIP currently conceptualizes the following for Watertown Plank Road.
* Minimal defective curb repair and overlay of a new asphalt surface from 124th Street to 115th Street.
* Defective curb repair and either complete pavement replacement or pulverization of existing pavement with a new asphalt surface from 115th Street to 113th Street.
* Complete street replacement from 113th Street to the bridge over the CP rail.
* New traffic signals at 115th Street and 116th Street.
* Multiuse trail on the north side from 124th Street to east of 113th Street.
* Sidewalk on the south side from 116th Street to east of 115th Street where the sidewalk currently ends.
* Sidewalk or multiuse trail connection from the Watertown Plank Road & 116th Street intersection south to the dead-end of 116th Street north of Diane Drive.

The Year 2025 115th Street pavement project extends from Watertown Plank Road to Underwood Parkway. The CIP currently conceptualizes the following for 115th Street.
* Defective curb repair and either c...

Click here for full text