Skip to main content
File #: 23-1040    Version: 1 Name:
Type: Report Status: Information Only
File created: 5/12/2023 In control: Board of Public Works
On agenda: 5/15/2023 Final action: 5/15/2023
Title: Project Updates

title
Project Updates

 

body

Submitted by:

Nicholas Deming

Department:

Engineering Division

 

21-47/48 Zoo Interchange North Leg (WisDOT Project)

                     Work and lane closures continue at the freeway overpasses at North Avenue and Mayfair Road to accommodate work overhead on the freeway structures.

                     Night work is anticipated for a deck pour the week of May 15th over Mayfair Road.

 

22-05 - 103rd St. Storm Sewer Relay

                     The contractor is continuing to install 5x6 box culvert on 103rd.  They should be close to reaching the end of 103rd and turning toward the easement late the week of May 8th.

                     They will continue box culvert installation and look to tie in to the existing structure late the week of May 15th.

                     Once complete with the box culvert, work will shift to install the catch basins and laterals.

 

22-08 - N 68th St.

                     The contractor is working on the punch list.

                     Street lighting work is being coordinated with WE Energies for the cabinet replacement around 66th & Cedar.

 

Project 1107 - North Avenue Reconstruction

                     The contractor is continuing work on the water main with one crew working on mainline and a second crew working to stub out tie ins on cross streets.

                     A 3rd crew is intended to be onsite for a couple weeks continuing work on sewer.

                     The contractor is aiming to start grading shortly after Memorial Day pending how upcoming work progresses and any weather impacts.

 

23-19 - 2023 Sidewalk Program

                     Work is starting on May 15th.