23-90 - 2023 Fiber
* Only a few hand holes remain uninstalled.
* Still awaiting permitting through the railroad. Remaining work pending at this time as coordination continues.
* Boring work started in a few locations. This work looks to resume the week of August 5th.

23-30 - Wauwatosa Bike Share
* Work to resume in fall in coordination with MRMC and the site work that is on-going.

Elm Grove Water Main Extension
* Water main work in Elm Grove continues through Summer/Fall 2024.

24-01 - Potter Road & 109th St.
* Water main work on Potter Road is near complete and ready for pressure testing and safe samples. The jacking and boring of the water main under the railroad is complete and awaiting tie in with the remainder of the water main being installed.
* Water main work across Mayfair Rd. (STH 100) is complete and the contractor was scheduled to complete the tie in of the new main to existing mains late last week.
* Concrete restoration near Mayfair is scheduled for the week of 7/29.
* Oak Leaf Trail paving is complete. Restoration is being coordinated with Milwaukee County Parks.
* The remaining tie-ins and service laterals are anticipated to be complete by August 9th.

24-02 - 116th St. Park
* Placement of fill is on-going with sources from the Potter Road project and the Elm Grove Water Main project.
* Mass grading activities are continuing and expected to generally wrap up the week of 8/5.
* Utility work for the sanitary lateral and water service started the week of 7/22.
* Storm sewer work on-site is scheduled to follow the utilities.
* Work on the retaining wall near Walnut is scheduled to begin the week of August 5th.

24-07 - 2024 Street Improvements
* Concrete removal is complete on Sarasota Pl. and Colonial Dr.
* Pulverizing of the existing pavement was scheduled for late the week of 7/22 on Sarasota Pl. and Colonial Dr.
* Restoration behind the curb will occur following pulverizing.
* Paving on Sarasota Pl. and Colonial...