title
Consideration of approval of final payment for Contract 23-24 / Project 1623 - 2023 Pavement Repair and Spot Improvements
body
Submitted by:
Nick Deming, Construction Manager
Department:
Engineering Division
Dear Board Members:
LaLonde Contractors, Inc. has completed the work of the 2023 Pavement Repair and Spot Improvements project and work incidental thereto under Contract 23-24 / Project 1623. The work took place at the intersection of the Menomonee River Parkway and North Avenue and the mid-block crossing between N. Pasadena Boulevard and N. 86th Street.
The final contract value due to the contractor is $150,885.02. The contract award amount was $139,978.17. The final amount due the contractor is $11,226.25. There was one change order on the contract that addressed a remobilization of equipment due to a scope change after work was complete and the addition of additional signage at the mid-block crossing for a net increase in the contract of $3,600.00. The need for 8” concrete base to restore pavement and an overrun in asphalt quantity resulted in the contract exceeding the original bid amount.
I hereby certify that the work on Contract 23-24 / Project 1623 was completed in a manner satisfactory to the City of Wauwatosa and recommend acceptance of the same by the Board of Public Works.
Sincerely,
Nick Deming, PE
Construction Manager
Enclosure(s):
23-24 Final Pay Application
recommendation
Recommendation: Common Council