Approval of Final Payment for Contract 24-07 2024 Street & Utility Improvements
body
Submitted by:
Mahmoud Jassar, Asst. Construction Manager
Department:
Engineering Department
Dear Board Members:
Stark Pavement Corp has completed the work for the 2024 Street & Utility Improvements under Contract 24-07/Project Number 324000007. The work took place on N 115th St, N Colonial Dr, & W Sarasota Pl.
The final contract value is $973,385.00. The original base bid was $989,999.00. The final amount due to the contractor is $239,639.47
The final contract value is less than the original bid amount by $16614 due to liquidated damages incurred.
I hereby certify that the work on Contract 24-07/Project 324000007 was completed in a manner satisfactory to the City of Wauwatosa and recommend acceptance of the same by the Board of Public Works.
Sincerely,
Mahmoud Jassar, PE
Asst. Construction Manager
Enclosure(s):
24-07 Pay App 4
recommendation