Project Updates
body
Project 1107 - North Avenue Reconstruction
• The contractor has the outside lanes close on North Avenue to complete repairs in the outside lanes and terrace areas.
• It is expected the contractor will move traffic to the outside lanes to begin repairs in the median in the next week to complete median tree plantings and repairs on the inside lanes.
• Pavement marking repairs are anticipated near the end of May.
23-90 - 2023 Fiber
• Hand hole installation is nearing completion.
• Contractor is taking a pause for a few weeks and will look to resume work in early/mid-June
23-30 - Wauwatosa Bike Share
• Work to resume in fall in coordination with MRMC and the site work that is on-going.
Elm Grove Water Main Extension
• Water main work in Elm Grove continues through early June.
24-01 - Potter Road & 109th St.
• Storm sewer is continuing from Underwood Creek heading south toward Potter.
• Work on the cast in place outfall and large sewer structures is underway.
24-02 - 116th St. Park
• A preconstruction meeting was held on May 17th.
• Placement of fill is on-going with sources from the Potter Road project and the Elm Grove Water Main project.
• Erosion control, tree protection and tree removal is expected to begin in late May/early June.
24-07 - 2024 Street Improvements
• Preconstruction Meeting Date TBD
24-11 - Green Alleys
• Work is underway with pavement repair along the side streets on 124th between Center St. and Burleigh Ave.
• Pavement repair work is expected into early June. Once complete, work will shift to the two alleys.
24-19 - 2024 Sidewalk Repair Program
• Ramp removal and replacement is complete.
• Sidewalk stone replacement is expected to start in early/mid June.
24-43 - Highlands Railing Replacement
• Bridge repair work is complete.
• Rail replacement is slated for early June.
WisDOT Zoo IC North Leg
• Swan Blvd. from Discovery Parkway west to Underwood Parkway is reopened.