File #: 25-0095    Version: 1 Name:
Type: Resolution-Council Status: Passed
File created: 1/15/2025 In control: Common Council
On agenda: 1/28/2025 Final action: 1/28/2025
Title: Final Resolution authorizing public improvement for repaving streets and alleys and levying special assessments against benefited properties
Related files: 24-1609, 24-1769, 24-1610, 24-1537, 24-1538
title
Final Resolution authorizing public improvement for repaving streets and alleys and levying special assessments against benefited properties

body
WHEREAS, the Common Council of the City of Wauwatosa, Wisconsin, held a public hearing both in-person and virtually via use of the Zoom platform at 7:30 p.m. Local Time, on the 17th day of December, 2024 for the purpose of hearing all interested persons concerning the preliminary resolution and report of the Board of Public Works on the proposed improvement by repaving of the following streets and alleys.

Street & Location: N. 115th St. from Underwood Pkwy. to Watertown Plank Rd.
Ald Dist: 3
Exist & Prop. Width: 36 (36)
Pavement Construction Type: D-Asph
Assessed Sidewalk Work: No

Street & Location: Watertown Plank Rd. from 113th St. to N. 115th St.
Ald Dist: 3 & 7
Exist & Prop. Width: 52 (52)
Pavement Construction Type: D-Asph
Assessed Sidewalk Work: No

Street & Location: Watertown Plank Rd. from 115th St. to N. 124th St.
Ald Dist: 3
Exist & Prop. Width: 52 (52)
Pavement Construction Type: E-Asph
Assessed Sidewalk Work: No

Street & Location: Wisconsin Ave. from N. 68th St. to N. 72nd St.
Ald Dist: 4
Exist & Prop. Width: 40 (40)
Pavement Construction Type: D-Asph
Assessed Sidewalk Work: Yes

Street & Location: Alley, Harvard Ln. to Blue Mound Rd. and N. 109th St. to N. 111th St.
Ald Dist: 3
Exist & Prop. Width: 20 (20)
Pavement Construction Type: A-Conc
Assessed Sidewalk Work: No

Reconstruction: Type "A" (Asph.) or (Conc.) Completely removing existing curb and gutter and existing pavement, placing new concrete curb and gutter (excluding alleys), and asphalt or concrete pavement surface on a new base.

The above repaving type also includes placing necessary water and sewer service pipes and storm sewer and appurtenances; relaying sanitary sewer and storm sewer as required; relocating existing street lighting system where necessary; constructing new concrete driveway approaches; an...

Click here for full text