Skip to main content
File #: 26-0112    Version: 1 Name:
Type: Action Item Status: Passed
File created: 1/9/2026 In control: Board of Public Works
On agenda: 1/21/2026 Final action:
Title: Consideration of request by the Engineering Division for approval of plans and specifications for Contract 26-07 / Project 1026 / 2026 Street & Utility Improvements. Project limits include Perry Court, Laurel Court, and Maple Terrace from 76th Street to 75th Street
Attachments: 1. 26-07_Resolution.pdf, 2. 26-07 BPW Project Manual_Plans.pdf

title
Consideration of request by the Engineering Division for approval of plans and specifications for Contract 26-07 / Project 1026 / 2026 Street & Utility Improvements. Project limits include Perry Court, Laurel Court, and Maple Terrace from 76th Street to 75th Street

 

body

Submitted by:

Jessica Henderson, P.E., Civil Engineer

Department:

Public Works, Engineering Division

 

A.                     Issue

Engineering is requesting approval of plans and specifications for Contract 26-07 / Project 1026 / 2026 Street & Utility Improvements. Project limits include Perry Court, Laurel Court, and Maple Terrace from 76th Street to 75th Street.

 

 

B.                     Background/Options 

Engineering has prepared the attached plans and specifications for this Street & Utility Improvements project. Project limits include Perry Court, Laurel Court, and Maple Terrace from 76th Street to 75th Street. The work is planned for the 2026 construction season.

 

 

C.                     Strategic Plan (Area of Focus)

Priority Area Three: Infrastructure

 

 

D.                     Fiscal Impact

Project 1026 has been included in the approved 2026-2030 Capital Budget.

 

 

E.                     Recommendation

Staff recommends approval of the plans and specifications and authorization be granted to the City Clerk to advertise for bids on Contract 26-07, Project 1026, 2026 Street & Utility Improvements Project.