Title: Project Updates

title
Project Updates

 

body

Submitted by:

Nick Deming, Construction Manager

Department:

Engineering

 

23-90 - 2023 Fiber

                     Awaiting DOT approval on revised permit.

 

25-01 - Wisconsin Avenue

                     Roadway work complete for winter. Permanent sidewalks to be installed in Spring ’26.

                     Signals to be installed upon delivery of signal poles.

 

25-07 - Watertown Plank Road

                     Contractor has shut down for winter. Work to resume in late Winter/early Spring ’26.

 

25-07 - 2025 Sanitary Sewer Improvements (Diane Dr. & Discovery Parkway)

                     Sanitary Sewer installed. Permanent restoration to be completed in Spring ’26.

 

25-25 - Burleigh St. Path and Asphalt Repair

                     Complete - Some punch list items will carry over into Spring 2026 due to current weather conditions.

 

Wisconsin Avenue Bridge (WisDOT Led)

                     Bridge was reopened in December over Honey Creek. Masonry work and wrap up items to be completed in Spring of ’26.