title
Project Updates
body
Submitted by:
Nick Deming, Construction Manager
Department:
Engineering
23-90 - 2023 Fiber
• Awaiting DOT approval on revised permit.
25-01 - Wisconsin Avenue
• Roadway work complete for winter. Permanent sidewalks to be installed in Spring ’26.
• Signals to be installed upon delivery of signal poles.
25-07 - Watertown Plank Road
• Contractor has shut down for winter. Work to resume in late Winter/early Spring ’26.
25-07 - 2025 Sanitary Sewer Improvements (Diane Dr. & Discovery Parkway)
• Sanitary Sewer installed. Permanent restoration to be completed in Spring ’26.
25-25 - Burleigh St. Path and Asphalt Repair
• Complete - Some punch list items will carry over into Spring 2026 due to current weather conditions.
Wisconsin Avenue Bridge (WisDOT Led)
• Bridge was reopened in December over Honey Creek. Masonry work and wrap up items to be completed in Spring of ’26.