Title: Project Updates

title
Project Updates

 

body

Submitted by:

Nick Deming, Construction Manager

Department:

Engineering

 

23-90 - 2023 Fiber

•                     Awaiting DOT approval on revised permit.

 

25-01 - Wisconsin Avenue

•                     Roadway work complete for winter. Permanent sidewalks to be installed in Spring ’26.

•                     Signals to be installed upon delivery of signal poles.

 

25-07 - Watertown Plank Road

•                     Contractor has shut down for winter. Work to resume in late Winter/early Spring ’26.

 

25-07 - 2025 Sanitary Sewer Improvements (Diane Dr. & Discovery Parkway)

•                     Sanitary Sewer installed. Permanent restoration to be completed in Spring ’26.

 

25-25 - Burleigh St. Path and Asphalt Repair

•                     Complete - Some punch list items will carry over into Spring 2026 due to current weather conditions.

 

Wisconsin Avenue Bridge (WisDOT Led)

•                     Bridge was reopened in December over Honey Creek. Masonry work and wrap up items to be completed in Spring of ’26.