Title: Resolution approving an amendment to the professional services agreement with MSA, in the amount of $400,000, for continued stormwater modeling and preliminary engineering analysis of the Schoonmaker Creek Watershed, CIP Project 3005
Attachments: 1. R-25-48 - Approving amendment to PSA with MSA for continued stormwater modeling and preliminary engineering analysis of the Schoonmaker Creek Watershed
Related files: 25-0561

title
Resolution approving an amendment to the professional services agreement with MSA, in the amount of $400,000, for continued stormwater modeling and preliminary engineering analysis of the Schoonmaker Creek Watershed, CIP Project 3005

 

body

WHEREAS, the City of Wauwatosa entered into a professional services agreement with MSA to complete a detailed analysis to address flooding in the Schoonmaker Creek Watershed in 2023; and

 

WHEREAS, the City and MSA have worked with the Milwaukee Metropolitan Sewage District to develop a scope of services for the next phase of work related to Schoonmaker Creek and the city is recommending an amendment to MSA’s current agreement to finalize the effort in the next 9-12 months.

 

NOW, THEREFORE, BE IT RESOLVED by the Common Council of the City of Wauwatosa that funds from Project 3005 be used to for the revision of the professional services agreement with MSA by authorization of the additional work at a cost of up to $400,000 for a new total agreement amount of $850,000.00.

 

 

By: Financial Affairs Committee

 

recommendation

Recommendation: Approve 7-0