title
Project Updates
body
23-90 - 2023 Fiber
• Updating permit with DOT.
25-01 - Wisconsin Avenue
• Work at 76th & Wisconsin is underway with storm sewer installation and under ground work for the new signals taking place over the next few weeks.
• Curb work, signal bases and pavement are expected to follow, in generally that order once underground work is complete.
25-07 - Watertown Plank Road
• Grading for the path on 116th St. is nearly complete. Will be paved in spring due to temperatures.
• Installation of Box Culvert is paused as the sanitary sewer is relocated ahead of the box culvert installation.
• Grading and roadway work are also underway on the EB lanes of Watertown Plank Road between 115th Street and the railroad bridge.
25-07 - 2025 Sanitary Sewer Improvements (Diane Dr. & Discovery Parkway)
• Work on Diane Dr. is complete
• SB Discovery will close late the week of 11/3 while sanitary sewer installation takes place.
• Excavation for bore pits scheduled for week of 11/10.
25-25 - Burleigh St. Path and Asphalt Repair
• Complete - Punch List Underway
Wisconsin Avenue Bridge (WisDOT Led)
• Channel realignment of the creek is continuing the week of 11/3
• Deck pour scheduled for 11/3
• Roadway work is underway on Wisconsin Avenue and Honey Creek Parkway and is expected to continue over the next couple weeks.
DPW Incinerator Demolition
• The above ground portion of the building has been removed.
• Below grade removal of the foundation is underway.