Approval of Final Payment for Contract 24-91 Street Light Conversion
body
Submitted by:
Mahmoud Jassar, Asst. Construction Manager
Department:
Engineering Dept
Dear Board Members:
PGS Signal & Lighting LLC has completed the work for the 2024 Utility Improvements project and work incidental thereto under Contract 24-91 / Projects 2403 and 2405. The work took place on multiple streets across the City.
The final contract value is $255,887.66. The contract award amount was $247,733.97. The final amount due to the contractor is $32,530.94. The final contract value is more than the original bid amount as a Change Order was needed for adding reducers to poles for Fixtures.
I hereby certify that the work on Contract 24-91 / Project 2403 and 2405 was completed in a manner satisfactory to the City of Wauwatosa and recommend acceptance of the same by the Board of Public Works.
Sincerely,
Mahmoud Jassar, PE
Asst. Construction Manager
Enclosure(s):
24-91 Pay App #5
24-91 CO#1
recommendation
Recommendation: Common Council