Title: Project Updates

title
Project Updates

 

body

Submitted by:

Nick Deming, Construction Manager

Department:

Engineering

 

23-90 - 2023 Fiber

                     Railroad flagging for the bore shot on 115th St. is scheduled in early January.

                     An updated permit was received from WisDOT.  The City is awaiting the schedule from the contractor on when fiber will begin being installed and spliced into the network.

 

23-30 - Wauwatosa Bike Share

                     Substantially complete.

 

Elm Grove Water Main Extension

                     The remaining water main has been dedicated to the City of Wauwatosa

                     Additional lateral work will resume once weather is favorable in the spring of 2025.

 

24-01 - Potter Road & 109th St.

                     Work is generally complete for 2024.

                     Work on street lighting will continue over the next few weeks.

                     Work on 109th St. will take place in 2025 based on current progress on the project.

 

24-02 - 116th St. Park

                     Landscaping and work on the playground area are on-going.

                     Site stabilization is in process

                     Work on the retaining wall on the south end of the project has started.

 

24-07 - 2024 Street Improvements

                     Substantially complete.