title
Project Updates
body
Submitted by:
Nick Deming, Construction Manager
Department:
Engineering
23-90 - 2023 Fiber
• Railroad flagging for the bore shot on 115th St. is scheduled in early January.
• An updated permit was received from WisDOT. The City is awaiting the schedule from the contractor on when fiber will begin being installed and spliced into the network.
23-30 - Wauwatosa Bike Share
• Substantially complete.
Elm Grove Water Main Extension
• The remaining water main has been dedicated to the City of Wauwatosa
• Additional lateral work will resume once weather is favorable in the spring of 2025.
24-01 - Potter Road & 109th St.
• Work is generally complete for 2024.
• Work on street lighting will continue over the next few weeks.
• Work on 109th St. will take place in 2025 based on current progress on the project.
24-02 - 116th St. Park
• Landscaping and work on the playground area are on-going.
• Site stabilization is in process
• Work on the retaining wall on the south end of the project has started.
24-07 - 2024 Street Improvements
• Substantially complete.