Title: Project Updates

title
Project Updates

 

body

Submitted by:

Nick Deming, Construction Manager

Department:

Engineering

 

23-90 - 2023 Fiber

•                     Railroad flagging for the bore shot on 115th St. is scheduled in early January.

•                     An updated permit was received from WisDOT.  The City is awaiting the schedule from the contractor on when fiber will begin being installed and spliced into the network.

 

23-30 - Wauwatosa Bike Share

•                     Substantially complete.

 

Elm Grove Water Main Extension

•                     The remaining water main has been dedicated to the City of Wauwatosa

•                     Additional lateral work will resume once weather is favorable in the spring of 2025.

 

24-01 - Potter Road & 109th St.

•                     Work is generally complete for 2024.

•                     Work on street lighting will continue over the next few weeks.

•                     Work on 109th St. will take place in 2025 based on current progress on the project.

 

24-02 - 116th St. Park

•                     Landscaping and work on the playground area are on-going.

•                     Site stabilization is in process

•                     Work on the retaining wall on the south end of the project has started.

 

24-07 - 2024 Street Improvements

•                     Substantially complete.