title
Approval of Final Payment for Contract 21-55 Blanchard Street Pumping Station Modifications
body
Submitted by:
Adam Florin
Department
Water Department
Dear Board Members:
Midwest General & Mechanical Contractors has completed the work of the Blanchard Street Pumping Station Modifications and work incidental thereto under Contract 21-55 / Project 5101. The work took place at 7300 Blanchard Street.
The final contract value due to the contractor is $1,270,980.00. The contract award amount was $1,215,655.00. The final amount due the contractor is $81,290.25. There were two change orders on the contract that addressed the relocation of the generator concrete pad and process piping modifications for a net increase in the contract of $60,065.00. There was one additional change order that addressed electrical parts not used on the project for a net decrease in the contract of $4,740.00.
I hereby certify that the work on Contract 21-55 / Project 5101 was completed in a manner satisfactory to the City of Wauwatosa and recommend acceptance of the same by the Board of Public Works.
recommendation
Recommendation: Common Council