Skip to main content
File #: 26-0031    Version: Name:
Type: Action Item Status: Passed
File created: 12/22/2025 In control: Board of Public Works
On agenda: 1/21/2026 Final action:
Title: Approval of Final Payment for Contract 24-24 Alley Repair Project
Attachments: 1. Pay App #3 -Executed
Related files: 26-0204

title
Approval of Final Payment for Contract 24-24 Alley Repair Project

 

body

Submitted by:

Mahmoud Jassar, Asst. Construction Manager

Department:

Engineering Department

 

Dear Board Members:

 

Stark Pavement Corp has completed the work for the 2024 Alley Repair Project under Contract 24-24/ Project Number 324000013. The work took place on multiple alleys across the city.

 

The final contract value is $292,278.13 with the original base bid of $266,504.50. The final amount due to the contract is $77,925.47. The final contract value is more than the original bid amount by $25,773.63 as a change order was needed for tree trimming at two properties, use of 7-bag concrete on an alley, structure repair, casting replacement, and adjustment of quantities on Capitol Dr.

 

I hereby certify that the work on Contract 24-24 /Project 324000013 was completed in a manner satisfactory to the City of Wauwatosa and recommend acceptance of the same by the Board of Public Works.

 

Sincerely,

Mahmoud Jassar, PE

Asst. Construction Manager

 

Enclosure(s):

 

24-24 Pay App 3

 

 

 

recommendation

Recommendation: Common Council