Title: Resolution approving the contract modification for Contract 26-11, 2026 Green Alley, in the amount of $54,352.60
Related files: 26-1511
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title
Resolution approving the contract modification for Contract 26-11, 2026 Green Alley, in the amount of $54,352.60

 

body

WHEREAS, a contract modification has been prepared for Contract 26-11, Project No. 10262, 2026 Green Alley; and

 

WHEREAS, the contract modification provides for additional work associated with the installation of speed humps, signage, and pavement markings at Hart Park and Kavanaugh Place; and

 

WHEREAS, the amount of the contract modification is $54,352.60, increasing the contract total from $319,609.11 to $373,961.71; and

 

WHEREAS, funding for this contract modification is available in the traffic calming project fund.

 

NOW, THEREFORE, BE IT RESOLVED by the Common Council of the City of Wauwatosa that the contract modification for Contract 26-11, Project No. 10262, 2026 Green Alley, in the amount of $54,352.60 is hereby approved.

 

 

By: Board of Public Works

 

recommendation

Recommendation: Approve 4-0