Title: Approval of Final Payment for Project1024 / Contract 24-08 2024 Utility Improvements
Attachments: 1. 24-08 Pay App 4 - Fully Executed

title
Approval of Final Payment for Project1024 / Contract 24-08 2024 Utility Improvements

 

body

Dear Board Members:

 

Soper Sewer & Water, LLC. has completed the work of the 2024 Utility Improvements project and work incidental thereto under Contract 24-08 / Project 1024.  The work took place on Center Street between 116th Street and 118th Street.

 

The final contract value is $1,377,274.50. The contract award amount was $1,661,869.41.  The final amount due the contractor is $52,738.01. The final contract value is less than the original bid amount as the work on Discovery Parkway was removed from the contract.

 

I hereby certify that the work on Contract 24-08 / Project 1024 was completed in a manner satisfactory to the City of Wauwatosa and recommend acceptance of the same by the Board of Public Works.

 

 

Sincerely,

 

Nick Deming, PE

Construction Manager

 

 

Enclosure(s):

24-08 Pay App #4

24-08 Change Order #2

 

 

By: Board of Public Works

 

recommendation

Recommendation: Common Council