WHEREAS, the City has solicited bids for Contract 26-11 / Project 10262, 2026 Green Alley, which includes construction of permeable pavers, storm sewer underdrain installation, and storm sewer lining for the alley from Mayfair Road to 102nd Street, between North Avenue and Beverly Place; and
WHEREAS, two (2) bids were received and publicly opened on April 15, 2026; and
WHEREAS, the bids received were as follows:
All-Ways Contractors, Inc. - $307,635.55
LaLonde Contractors, Inc. - $319,609.11; and
WHEREAS, All-Ways Contractors, Inc. submitted the lowest and best bid; and
WHEREAS, Project 10262 is included in the adopted 2026-2031 Capital Budget;
NOW, THEREFORE, BE IT RESOLVED by the Common Council of the City of Wauwatosa that Contract 26-11 / Project 10262, 2026 Green Alley, is hereby awarded to All-Ways Contractors, Inc. in the amount of $307,635.55; and
BE IT FURTHER RESOLVED that the appropriate City officials are hereby authorized to execute the contract and take all necessary actions to implement this project.
By: Board of Public Works
recommendation
Recommendation: Approve 4-0