23-90 - 2023 Fiber

                     The contractor is looking to start pulling fiber once the WisDOT permit extension is received.

 

24-01 - Potter Road & 109th St.

                     Grading and curb work are on-going on 109th St.

                     The multiuse path construction on Potter has resumed with school no longer in session.

 

25-01 - Wisconsin Avenue

                     68th St. at Wisconsin is closed to facilitate water and sewer construction. It is expected to be closed through the summer to install utilities and reconstruct the intersection.

                     Storm sewer work started and will continue for the next few weeks on 70th St.

 

25-07 - Watertown Plank Road

                     Water main work is underway.

                     The outfall channel was cleared and reviewed for areas needing repair.

                     Outfall and Storm Sewer work is expected to start as materials arrive in July.

 

25-08 - Center Street

                     Preconstruction meeting was held. Awaiting a schedule and start date from the contractor.

 

25-19 - 2025 Sidewalk Program

                     Sidewalk program work is underway with both ramp reconstruction and replacement of sidewalk.

 

25-25 - Burleigh St. Path and Asphalt Repair

                     A preconstruction meeting is scheduled for the week of 6/23.

 

Wisconsin Avenue Bridge (WisDOT Led)

                     Bridge demolition is complete.

                     The new bridge abutments on either side of the creek are being constructed.