Title: Project Updates

title
Project Updates

 

body

Submitted by:

Nick Deming, Construction Manager

Department:

Engineering

 

23-90 - 2023 Fiber

•                     The contractor is looking to start pulling fiber once the WisDOT permit extension is received.

 

24-01 - Potter Road & 109th St.

•                     Grading and curb work are on-going on 109th St.

•                     The multiuse path construction on Potter has resumed with school no longer in session.

 

25-01 - Wisconsin Avenue

•                     68th St. at Wisconsin is closed to facilitate water and sewer construction. It is expected to be closed through the summer to install utilities and reconstruct the intersection.

•                     Storm sewer work started and will continue for the next few weeks on 70th St.

 

25-07 - Watertown Plank Road

•                     Water main work is underway.

•                     The outfall channel was cleared and reviewed for areas needing repair.

•                     Outfall and Storm Sewer work is expected to start as materials arrive in July.

 

25-08 - Center Street

•                     Preconstruction meeting was held. Awaiting a schedule and start date from the contractor.

 

25-19 - 2025 Sidewalk Program

•                     Sidewalk program work is underway with both ramp reconstruction and replacement of sidewalk.

 

25-25 - Burleigh St. Path and Asphalt Repair

•                     A preconstruction meeting is scheduled for the week of 6/23.

 

Wisconsin Avenue Bridge (WisDOT Led)

•                     Bridge demolition is complete.

•                     The new bridge abutments on either side of the creek are being constructed.