File #: 23-583    Version: 1 Name:
Type: Action Item Status: Passed
File created: 8/24/2023 In control: Board of Public Works
On agenda: 9/5/2023 Final action:
Title: Consideration of approval of Change Order Number 2 for Contract 21-55 Blanchard Street Pumping Station
Attachments: 1. BPW Staff Memo-Contract 21-55 Change Order No. 2
Related files: 23-627

title
Consideration of approval of Change Order Number 2 for Contract 21-55 Blanchard Street Pumping Station

 

body

A. Issue

City staff is requesting approval of Change Order Number 2 for Contract 21-55 Blanchard Street Pumping Station in the amount of $38,365.

B. Background

Per the attached change order description, during the installation of the new process water pipe in the Blanchard Street pumping station it was determined the proposed alignment would interfere with an existing steel support beam. Piping modifications will need to be made for the realignment of this process piping and new water pumps. Also, the existing concrete water pump bases are at different elevations than the new pumps provided. Pump base and piping modifications will be needed to align the existing process piping to the new pumps.

C. Fiscal Impact

The contract price prior to this change order was $1,237,355. The new contract price incorporating this change order of $38,365 will be $1,275,720. The original 2021-2025 CIP budget for the contract was $1,300,000.

D. Recommendation

Approval of Change Order Number 2 for Contract 21-55 Blanchard Street Pumping Station in the amount of $38,365.

 

 

recommendation

Recommendation: Common Council Approval