File #: 23-627    Version: 1 Name:
Type: Resolution-Council Status: Passed
File created: 9/1/2023 In control: Common Council
On agenda: 9/5/2023 Final action: 9/5/2023
Title: Resolution approving Change Order Number 2 for Contract 21-55 Blanchard Street Pumping Station
Attachments: 1. R-23-157 - Approving Change Order Number 2 for Contract 21-55 Blanchard Street Pumping Station
Related files: 23-583

By: Board of Public Works

 

title
Resolution approving Change Order Number 2 for Contract 21-55 Blanchard Street Pumping Station

 

body

WHEREAS, the Board of Public Works is requesting a change order to Contract 21-55 to the Blanchard Street Pumping Station to align the existing process piping to new pumps; 

 

WHEREAS, the estimated total cost of the scope changes within Change Order #02 is $38,365;

 

NOW, THEREFORE, BE IT RESOLVED by the Common Council of the City of Wauwatosa that a change order for piping modifications for the realignment of process piping and new water pumps be approved.

 

 

recommendation

Recommendation: Approve 6-0