By: Board of Public Works
title
Resolution approving Change Order Number 2 for Contract 21-55 Blanchard Street Pumping Station
body
WHEREAS, the Board of Public Works is requesting a change order to Contract 21-55 to the Blanchard Street Pumping Station to align the existing process piping to new pumps;
WHEREAS, the estimated total cost of the scope changes within Change Order #02 is $38,365;
NOW, THEREFORE, BE IT RESOLVED by the Common Council of the City of Wauwatosa that a change order for piping modifications for the realignment of process piping and new water pumps be approved.
recommendation
Recommendation: Approve 6-0