Title: Approval of Final Payment for Contract 23-07 N 115th Street Improvements
Attachments: 1. 23-07 Payment 5 - Final - signed 01-14-26
Related files: 26-0203

title
Approval of Final Payment for Contract 23-07 N 115th Street Improvements

 

body

Submitted by:

Mahmoud Jassar, Asst. Construction Manager

Department:

Engineering Department

 

Dear Board Members:

Stark Pavement Corp has completed the work for the N 115th STREET IMPROVEMENTS under Contract 23-07/Project Number 323000008. The work took place on N 115th St and Potter Rd.

The final contract value is $1,707,562.72. The original base bid was $1,619,104.01. The final amount due to the contract is $147,525.50.

The final contract value is more than the original bid amount by $88,458.71 as three (3) change orders were needed relating to increased pavement quantity, project delays, and utility interference with proposed storm sewer.

I hereby certify that the work on Contract 23-07/Project 323000008 was completed in a manner satisfactory to the City of Wauwatosa and recommend acceptance of the same by the Board of Public Works.

 

Sincerely,

Mahmoud Jassar, PE

Asst. Construction Manager

 