title
Project Updates
body
Submitted by:
Nick Deming, Construction Manager
Department:
Engineering
23-90 - 2023 Fiber
• Work has started to finish conduit and handhole installation within WisDOT right of way.
• Work is on-going.
• Elm Grove Water Main Extension
• The remaining water main has been dedicated to the City of Wauwatosa
• Additional lateral work will resume once weather is favorable in the spring of 2025.
• 24-01 - Potter Road & 109th St.
• Work on 109th St. is resuming the week of March 10th.
24-02 - 116th St. Park
• Work on the retaining wall on the south end of the project is ongoing along with certain items around the playground area.
• Work is expected to pick up on late March and early April as the weather breaks.
25-01 Wisconsin Avenue
• Preconstruction meeting to be held Friday, March 14th
• Work expected to begin in late March or Early April
25-07 Watertown Plank/116th/115th
• Preconstruction meeting to be held in Early April
• Work expected to begin around Mid-April
Wisconsin Ave Bridge
• WE Energies Gas is closing Wisconsin Ave ahead of the Wisconsin Avenue Bridge project the week of March 10th.