Legislation Details

File #: 25-0408    Version: 1 Name:
Type: Report Status: Information Only
File created: 3/7/2025 In control: Board of Public Works
On agenda: 3/12/2025 Final action: 3/12/2025
Title: Project Updates

title
Project Updates

 

body

Submitted by:

Nick Deming, Construction Manager

Department:

Engineering

 

23-90 - 2023 Fiber

•                     Work has started to finish conduit and handhole installation within WisDOT right of way.

•                     Work is on-going.

 

•                     Elm Grove Water Main Extension

•                     The remaining water main has been dedicated to the City of Wauwatosa

•                     Additional lateral work will resume once weather is favorable in the spring of 2025.

 

•                     24-01 - Potter Road & 109th St.

•                     Work on 109th St. is resuming the week of March 10th.

24-02 - 116th St. Park

•                     Work on the retaining wall on the south end of the project is ongoing along with certain items around the playground area.

•                     Work is expected to pick up on late March and early April as the weather breaks.

 

25-01 Wisconsin Avenue

•                     Preconstruction meeting to be held Friday, March 14th

•                     Work expected to begin in late March or Early April

 

25-07 Watertown Plank/116th/115th

•                     Preconstruction meeting to be held in Early April

•                     Work expected to begin around Mid-April

 

Wisconsin Ave Bridge

•                     WE Energies Gas is closing Wisconsin Ave ahead of the Wisconsin Avenue Bridge project the week of March 10th.