Title: Project Updates

title
Project Updates

 

body

Submitted by:

Nick Deming, Construction Manager

Department:

Engineering

 

23-90 - 2023 Fiber

                     Work has started to finish conduit and handhole installation within WisDOT right of way.

                     Work is on-going.

 

                     Elm Grove Water Main Extension

                     The remaining water main has been dedicated to the City of Wauwatosa

                     Additional lateral work will resume once weather is favorable in the spring of 2025.

 

                     24-01 - Potter Road & 109th St.

                     Work on 109th St. is resuming the week of March 10th.

24-02 - 116th St. Park

                     Work on the retaining wall on the south end of the project is ongoing along with certain items around the playground area.

                     Work is expected to pick up on late March and early April as the weather breaks.

 

25-01 Wisconsin Avenue

                     Preconstruction meeting to be held Friday, March 14th

                     Work expected to begin in late March or Early April

 

25-07 Watertown Plank/116th/115th

                     Preconstruction meeting to be held in Early April

                     Work expected to begin around Mid-April

 

Wisconsin Ave Bridge

                     WE Energies Gas is closing Wisconsin Ave ahead of the Wisconsin Avenue Bridge project the week of March 10th.